03 January 2012
Supreme Court
Download

DARSHAN LAL NAGPAL Vs GOVT.OF NCT OF DELHI .

Bench: G.S. SINGHVI,SUDHANSU JYOTI MUKHOPADHAYA
Case number: C.A. No.-011169-011169 / 2011
Diary number: 3005 / 2011
Advocates: J S WAD AND CO Vs SUDARSHAN RAJAN


1

REPORTABLE IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO. 11169 OF 2011

Darshan Lal Nagpal (dead) by L.Rs.  … Appellants

versus

Government of NCT of Delhi and others … Respondents

J U D G M E N T

G. S. Singhvi, J.

1. The questions which arise for consideration in this appeal are whether the  

Government of NCT of Delhi could have invoked Section 17(1) and (4)  

of the Land Acquisition Act, 1894 (for short, ‘the Act’) and dispensed  

with  the  rule  of  hearing  embodied  in  Section  5A(2)  thereof  for  the  

purpose of acquiring land measuring 80 bighas 15 biswas including 21  

bighas 3 biswas belonging to the appellants for a public purpose, namely,  

establishment of electric sub-station by Delhi Transco Limited (for short,  

‘DTL’) at village Mandoli and whether the Division Bench of the Delhi  

1

2

High  Court  had  rightly  negatived  the  appellants’  challenge  to  the  

acquisition of their land.   

2. For deciding the aforesaid questions, it will be useful to notice the events  

which led to the issue of notification dated 13.10.2009 under Section 4(1)  

read  with  Section  17(1)  and  (4)  of  the  Act  and  declaration  dated  

9.11.2009 under Section 6(1) of the Act.

2.1  It is not clear from the pleadings of the parties and the record produced  

before the High Court  and this Court  as to when the decision was taken to  

establish 400/220 KV sub-station at East of Loni Road but this much is evident  

that by a communication sent in August, 2004, the DTL requested the Delhi  

Development Authority (for short, ‘the DDA’) for allotment of land.  For the  

next about 10 months nothing appears to have happened. Between June and  

October, 2005 different functionaries of DTL made some correspondence inter-

se in the matter of establishment of the sub-station. On 5/6.12.2005, Manager  

(400/220 KV SS&L) sent a communication to the Commissioner (Planning),  

DDA  wherein  he  emphasized  that  establishment  of  the  sub-station  was  

necessary  to  meet  the  power  demand  of  East  Delhi  and  particularly  the  

upcoming Commonwealth Games.  In his reply dated 8.2.2006, Joint Director  

(MP), DDA informed the DTL that allotment of sites suggested by it  is not  

2

3

feasible because site ‘A’ was developed as a park and site ‘B’ was earmarked as  

a community centre.  

2.2 Between January, 2006 and July, 2008, the officers of the DTL, the DDA  

and  the  Government  of  N.C.T.  of  Delhi  exchanged  letters  on  the  issue  of  

allotment of land for the sub-station.  While the officers of DTL stressed the  

need for early allotment of land, the officers of the DDA repeatedly expressed  

their  inability  to  allot  the  particular  site  by  pointing  out  that  the  same  was  

reserved for other purpose. On 28.07.2008, Secretary (Power), Government of  

NCT of Delhi-cum-CMD, DTL requested the DDA to change the land use of  

the particular site and inform the Government of N.C.T. of Delhi so that action  

could be taken for the acquisition of land under Section 17 of the Act.  In that  

letter, it was also mentioned that due to paucity of land, the DTL has proposed  

to establish a GIS indoor type sub-station which could be accommodated in a  

space of about 200 x 125 meters as against the original requirement of 700 x  

500 meters. The relevant portions of that letter are extracted below:

“In  pursuance  of  above,  a  meeting  was  held  with  Vice- Chairman, DDA on 06.05.2008 wherein a request was made  for  the allotment  of  land in East  Delhi.  Officers  of  Delhi  Transco  Limited,  State  Transmission  Utility,  along  with  Officers of DDA and the concerned ADM of the area had  identified the land in their joint inspection held on 30 th June,  2008. Copy of Khasra Nos. and their Report is enclosed as  Annexure-I. However, in the meantime DDA informed that  

3

4

the land in question is not acquired by DDA. It was further  informed  that  as  per  Master  Plan,  Agriculture/Green  area  can  be  utilized  for  Utilities.  Copy  of  the  letter  No.  F.6(4)2004/MP/D-127  dated  19.5.2008  is  enclosed  as  Annexure-II.  Since the establishment of the Grid Station is  of paramount importance for strengthening the power supply  in East Delhi, DDA is requested to change the land use and  to inform GNCTD so that action be taken for acquisition of  the same under Section 17, i.e., for the public utility.

Earlier it was proposed to construct an outdoor 400/200 KV  Grid Station but keeping in view the paucity and availability  of land DTL has now proposed to establish a GIS indoor  type sub-station which could be accommodated in a space of  about 200 x 125 meters. It shall be appreciated if appropriate  directions are issued to the concerned officers for doing the  needful expeditiously.”

(underlining is ours)

2.3 After  about  one  month,  Joint  Secretary  (Power)  sent  communication  

dated 9.9.2008 to the Principal Secretary, Land and Building Department with  

the request that action may be initiated for the acquisition of the identified piece  

of land by invoking Section 17 of the Act.  The relevant portions of that letter  

are extracted below:

“Hon’ble Prime Minister of India has laid the foundation  for  1500  KV  gas  based  power  plant  at  Bawana  on  24.03.2008  being  constructed  by  Pragati  Power  Corporation Limited, a company owned by Govt, of NCT  of Delhi in order to evacuate and utilize the generation  from this  plant  for  the  benefit  of  Delhi,  a  study  was  conducted  by  Central  Electricity  Authority  which  has  recommended the establishment of a 220 KV substation  in East Delhi for evacuation of power.

4

5

Officers of Delhi Transco Limited along with officers of  DDA  and  concerned  ADM  have  identified  the  land  measuring 200 M x 150 M in East Delhi for the proposed  grid. Copy of Khasra Nos. and their report is enclosed at  Annexure-1. Sketch showing broad location of the plot  proposed  to  be  acquired  with  Khasra  Nos.  of  the  proposed location is at Annexure-II. DDA has informed  that  the  land  in  question  is  not  acquired  by  DDA.  However,  as  per  Master  Plan 2021,  public  utilities  are  permitted  in  all  use  zones.  In  this  regard,  a  copy  of  Director  (Planning)  DDA  letter  dated  19.05.2008  is  enclosed as Annexure-III. The proposed site has already  been taken up with  VC,  DDA for  change of  land use  (Annexure-IV).

The commissioning of 155 MW power plant at Bawana  is  scheduled  before  the  Commonwealth  Games  in  October-2010.  Therefore,  keeping in  view the  urgency  involved,  kindly  initiate  the  process  for  acquisition  of  identified  peace  of  land  in  East  Delhi  in  favour  of  Department of Power, GNCTD as provided under section  17 of the Land Acquisition Act at the very earliest.”

(underlining is ours)

Soon thereafter, the Land and Building Department sent letter dated 30.9.2008  

to Additional District Magistrate-cum-Land Acquisition Collector (North-East)  

to send the following information/documents:

“1. Draft notification u/s 4, 6 and 17 along with the copy of Aks Sizra,  

field book etc.

2. Report after conducting Joint Survey.

3. 80% estimated compensation amount with Calculation Sheet.”

5

6

2.4 After about six months, Deputy General Manager (Planning-I), DTL sent  

letter dated 6.3.2009 to Deputy Secretary (Land Acquisition) and informed him  

that land measuring 250 x 200 sq. mts. with approach road will be required to  

accommodate  the  proposed  three  voltage  level  equipment  as  against  the  

requirement of 200 x 125 sq. mts. indicated in the earlier communications.  The  

concerned officer  also requested that the acquisition of 80 bighas 15 biswas  

land may be finalized as per the joint site inspection carried out on 12.01.2009.   

2.5 On its part, the DDA sent letter dated 8.5.2009 to the Deputy Secretary  

(Land Acquisition) that a joint site inspection be carried out for finalization of  

the site.  However, the latter sent communication dated 16.6.2009 to the DDA  

to issue NOC required for initiation of the acquisition proceedings.

2.6 In  September,  2009,  the  Land  and  Building  Department  of  the  

Government  of  NCT of Delhi  prepared proposal  for  the acquisition  of  land  

measuring 200 x 125 sq. mts. by invoking Sections 4 and 6 read with Section  

17(1)  and  (4)  of  the  Act.   This  is  evident  from  the  notings  recorded  in  

paragraphs  56 to  61 and  63 to  65 of  file  bearing No.  F.S(11)/08/L&B/LA,  

which are extracted below:  

“56. A requisition was received from Joint Secretary (Power)  Department of Power for acquisition of land measuring 200 x  125 Sq. m. identified in East Delhi for construction of 400 x  200  KV grid  station  (Village  Mandoli)  vide  their  letter  No.  

6

7

F.11(88)/2008/Power/2186  dated  09.09.2009  (P-6/C).  Accordingly,  the  ADM/LAC  (NE)  was  requested  for  draft  notifications  and  other  revenue  records  vide  letter  dated  30.09.2008 (P-7/C).

57. The ADM/LC (NE) vide his letter dated 31.01.2009 (P- 28/C) forwarded draft notification u/s 4 & 6 (P-26 & 27/C) for  acquisition of land measuring 80 Bigha 15 Biswa. Copy of Joint  Survey Report (P-23/C), copy of Field Book (P-20/C), copy of  Asks  Sizra   (P-19/C)  and  Calculation  Sheet  for  estimated  compensation amount (P-25/C).

58. The revenue staff  scrutinized the draft  notification and  some  discrepancies  have  been  found.  The  report  of  revenue  branch may be seen at page (P-5 & 6/N).

59. Accordingly, LAC (NE) was requested for clarification  vide letter dated 2/3/09 (page-29/C). A clarification was given  by LAC (NE) in aforesaid context and may be seen at P-32 to  39/C.  Report  of  revenue branch  may  be  seen  at  page  11 &  12/N.  Letter  dated  30/7/08  and  6/3/09  received  from  Delhi  Transco Ltd. regarding change of proposal may be seen at P.30  and 31/C. Delhi Transco Ltd. has given the justification for the  change  of  proposal  regarding  requirement  of  land,  i.e.,   80  Bigha 15 Biswa instead of 200 x 125 Sq.m.

60. Vide  letter  No.F.6(4)2004-MP/265  dated  7/9/09  Jt.  Director  (MP) DD has  informed that  DDA has  no objection  with  respect  to  proposed  location  of  land  for  establishing  400/200  KV  ESS  subject  to  compliance  of  the  following  conditions:-

a. Submission  of  a  layout  plan/location  plan  with  description of the land under reference be submitted to  ascertain the boundaries of the site.

b. Justification  for  an area of  6.8 hact.  against  2.96 hact.  required  for  establishment  of  200/400 KV ESS as  per  MPD-2021 norms.

c. This is a Master Plan level utility for which change of  land use will be processed after land is acquired.

7

8

d. Submission of transmission route alignment plan as the  surrounding area is thickly populated.

e. The site shall  not  be used for  any other purpose other  than ESS.

61. As the  matter  is  urgent  and related to  Commonwealth  Games, if approved Hon’ble L.G. may be requested to kindly  approve acquisition of land measuring 80 Bigha 15 Biswa as  per  the  draft  notifications  placed  opposite  for  acquisition  of  land for establishment of 400 x 200 KV sub-station in village- Mandoli and issuance of notification u/s 4 read with 17(4) and  section 6 along with 17(1) of Land Acquisition Act, 1894.

63. May  kindly  see  the  proposal  at  page  21/N  regarding  acquisition  of  land  measuring  80  Bigha  15  Biswa  for  construction of 400 x 200 KV grid station in village Mandoli.  The proposal has been received from Power Department, Govt.,  of NCT of Delhi, which is available at page 6/C. It has been  mentioned in the proposal that Hon’ble Prime Minister of India  has  laid  the  foundation  stone  for  155 MW gas  based  power  plant at Bawana on 24-3-2008 which is being constructed by  Pragati  Power  Corporation  Limited,  a  company  owned  by  Govt.,  of  NCT of  Delhi.  It  has  been  also  mentioned  in  the  proposal that to evacuate and utilize the generation from this  plant for the benefit of Delhi, a study was conducted by Central  Electricity  Authority  which  has  recommended  the  establishment  of  a  220  KV  sub-station  in  East  Delhi  for  evacuation of power. The Power Department has requested that  the acquisition of the above said land may be proceeded with  under the emergency provisions of the Land Acquisition Act  because  1500  MW  power  at  Bawana  is  scheduled  to  be  commissioned before the Commonwealth Games, 2010.

64. The  Land  Acquisition  Collector  (N/E)  has  prepared  a  draft notification under section 4 & 6 (page 26 & 27/C) after  conduction  the  Joint  survey  report  along  with  concerned  department  and  copy  of  the  same  is  available  at  page  23/C  along with relevant records. As per the joint survey available at  page 22/C and 23/C it appears that entire land is laying vacant  except to Bhattas (Brick Kiln) and boundary walls in 3 Khasras.  

8

9

The DDA has also provided no objection for acquisition subject  to  certain  conditions  as  mentioned  in  letter  dated  07-09-09,  which is available at page 64/C.

65. From the proposal  of the Power Department it  is clear  that land is required for valid public purpose and urgent need  for acquisition of the land has also been justified by the Power  Department. Therefore, if approved, Hon’ble Lt. Governor may  kindly be requested to approve acquisition of land measuring 80  Bigha 15 Biswa as per the draft notification placed opposite for  the public purpose namely for establishing 400 x 200 KV grid  sub-station  for  Power  Department  in  Village-Mandoli  and  issuance  of  notification  u/s  4  read  with  17(4)  and  section  6  along with 17(1) of Land Acquisition Act, 1894.”

2.7 The Lieutenant Governor of Delhi accorded his approval on 26.9.2009 in  

the following terms:  

“I  have  gone  through  the  records  and  requirement  of  Delhi  Transco  Ltd.  for  acquisition  of  land  for  Establishment  of  400x200  kv  station  at  village  Mandoli  and  the  draft  notifications prepared by LAC (North-East).

I am fully satisfied that the land measuring 80 Bigha 15 Biswa  is urgently required for above purpose.  In view of the urgency  of the scheme, I order that the provisions of section 5A shall not  apply and notifications under section 4 read with 17(4), 6 &  17(1) of the Land Acquisition Act, 1894 be issued immediately.

Sd/- Tejendra Khanna Lt. Governor Delhi 26.09.2009.”

3. In compliance  of  the direction given by the Lieutenant  Governor,  the  

Government  of  N.C.T.   of  Delhi  issued  notification  dated  13.10.2009  

9

10

under Section 4(1) read with Section 17(1) and (4) for the acquisition of  

80 bighas 15 biswas land. The declaration issued under Section 6(1) was  

published vide notification dated 9.11.2009. By another notification of  

the  same  date,  Land  Acquisition  Collector  (North-East),  Delhi  was  

authorised to take possession of the land on the expiry of 15 days.

4. When the appellants learnt about the proposed acquisition of their land,  

they made a representation to the Member of the Legislative Assembly  

that as per Master Plan of Delhi-2021 only 29.6 bigha land was required  

for the sub-station and that barren land available in the area could be  

utilized for that purpose leaving out their land. The concerned Member of  

the  Legislative  Assembly  forwarded  the  representation  to  the  

Government of NCT of Delhi on 28.4.2009 but the same did not yield the  

desired result and the notifications were issued under Section 4(1) read  

with Section 17(1) and (4) and Section 6(1) of the Act. Thereupon, the  

appellants  filed  Writ  Petition  No.  13376  of  2009  for  quashing  of  

notifications dated 13.10.2009 and 9.11.2009. The main plank of their  

challenge was that there was no urgency for the acquisition of land which  

could justify invoking of Section 17(1) and (4) of the Act.  They pleaded  

that  more  than  4  years  time  spent  in  the  correspondence  exchanged  

between the DTL, the State Government and the DDA clearly shows that  

10

11

there  was  no urgency  in  the  establishment  of  the  sub-station  and  the  

cause put forward by the DTL in 2008-2009, namely, the requirement of  

power for Commonwealth Games did not warrant invoking of Section  

17(1) and (4) which resulted in depriving them of their property without  

being heard. The appellants further pleaded that the Lieutenant Governor  

had not applied mind on the issue of urgency and approved the proposal  

prepared by the Land and Building Department, Government of NCT of  

Delhi  without satisfying himself  that  there  was emergent  need for  the  

acquisition  of  land  for  the  purpose  for  which  the  proposal  had  been  

initiated prior to August, 2004.  The appellants also claimed that other  

parcels of land including waste land belonging to the public authorities  

and  the  Gaon  Sabha  were  available,  which  could  be  utilized  for  

establishing  the  sub-station  but,  without  examining  the  feasibility  of  

acquiring  an  alternative  piece  of  land,  the  respondents   arbitrarily  

deprived them of their property.

5. In the counter affidavit  filed on behalf of the Government of NCT of  

Delhi and the Lieutenant Governor of Delhi it was averred that with a  

view to provide power to the city of Delhi, 1500 MW gas based power  

plant  was  being  constructed  at  Bawana  by  a  Government  owned  

company,  viz.,  Pragati  Power  Corporation  Limited;  that  the  plant  is  

11

12

scheduled to be commissioned in a time-bound manner in October, 2010  

before the commencement of the Commonwealth Games; that in order to  

evacuate  and  utilize  the  power  generated  from the  new plant  for  the  

benefit  of  Delhi,  the  Central  Electricity  Authority  recommended  

establishment of 220 KV sub-station in East Delhi; that after identifying  

the land in question the Power Department of Government of NCT of  

Delhi  made  a  request  for  initiation  of  the  acquisition  proceedings  on  

urgent basis;  that on receipt of letter dated 9.9.2008, instructions were  

issued  to  the  Land  Acquisition  Collector  to  conduct  a  joint  survey,  

prepare a draft notification and also make calculation of 80 per cent of  

the estimated compensation and that after taking all the necessary steps, a  

note  was  put  up  before  the  Lieutenant  Governor,  who  approved  the  

proposal for the acquisition of land under Section 4 read with Section  

17(1)  and  (4)  and  also  to  dispense  with  the  inquiry  envisaged  under  

Section 5A of the Act.  It  was also pleaded that the beneficiary of the  

acquisition deposited a sum of Rs.9,27,11,840/- towards 80 per cent of  

the estimated compensation as required by Section 17(3A) of the Act,  

which was remitted to the Land Acquisition Collector for payment.  In  

Para 11 of the counter affidavit it was averred that there is an urgent need  

12

13

of the land for the purpose of construction of sub-station by the DTL in  

the larger public interest.

6. In a separate written statement filed on behalf of the DTL it was pleaded  

that decision was taken by the Government to establish 400 / 220 KV  

grid sub-station to meet the growing demand of power in Delhi and the  

establishment  of  the  sub-station  was  approved  by  Delhi  Electricity  

Regulatory Commission vide order dated 16.6.2009. In paragraphs 5 to 7  

of the counter affidavit of the DTL reference was made to the decision  

taken by the Government to construct 1500 MW Pragati III Power Plant  

at Bawana IPGCL; 2 x 490 MW Thermal Power Stations at Dadri and  

1500  MW Thermal  Station  at  Jhajjar  and  also  to  establish  grid  sub-

stations for evacuation of power from different plants. According to the  

DTL, as per the Master Plan of Delhi-2021, the minimum land required  

for establishment of a conventional outdoor 400/220/66 KV sub-station is  

60 acres but because of scarcity of land, it was decided to establish an  

indoor GIS sub-station and for that purpose 80 bighas land was required.  

It was also the pleaded case of the DTL that the appellants’ land was  

identified after inspections carried out by the officers of the DDA, Land  

and Building Department,  Land Acquisition Collector,  Government  of  

13

14

NCT of Delhi and its own officers. In paragraphs 13, 14 and 15 of the  

counter affidavit of the DTL, the following averments were made:  

“13.  That  proposed  400KV  sub-station  cannot  be  established in  the 30 bighas  of  Gram Sabha land.  The  said  Gram  Sabha  land  does  not  fulfill  the  complete  purpose of the answering respondent because 80 bighas  are required for the establishment of the proposed sub- station.  Further,  the  said  Gram Sabha’s  land  does  not  give  any entrance  /  exit  point  towards  State  Highway.  Therefore, the acquisition of the said Gram Sabha’s land  does not serve any purpose.

14.  That  Delhi  Electricity  Regulatory  Commission,  which is a statutory body of Govt. of NCT of Delhi vide  its letter No. F.17(51)/Engg./DERC/2009-10/1074 dated  16.6.2009  granted  investment  approval  of  scheme  for  supply testing and commissioning of 400/220/66KV GIS  sub-station at East of Loni Road to the tune of Rs. 250.24  crores.  The  true  copy  of  the  letter  dated  16.6.2009  is  marked and annexed as Annexure – E.

15. Further the Power Grid Corporation of India Ltd. vide  its  letter  dated  28.8.2009  addressed  to  the  answering  respondent  emphasized  on  the  urgency  regarding  the  setting  up  and commission  of  the  400  KV sub-station  East  of Loni Road since the transmission line is being  constructed  for  catering  the  additional  load  of  Commonwealth Games, 2010 from 2 x 490 MW, NTPC  Dadri  Power  Plant  (under  construction)  and  set  the  timeline  of  completion  by  June,  2010.  It  was  further  pointed out that location of Lone Road sub-station and  coordinates of 400 KV switch yard gantry were urgently  required for the completion of the survey work. the true  copy of the letter dated 28.8.2009 is marked and annexed  as  Annexure  –  F.  Therefore,  it  was  a  comprehensive  scheme consisting of establishment  of 400/220KV grid  sub-station by the answering respondent whereas in feed  i.e.  400  KV  transmission  line  from  Dadri  Generating  

14

15

Station upto the proposed grid sub-station at East of Loni  Road.”

7. The  Division  Bench  of  the  High  Court  noticed  the  correspondence  

exchanged between the DTL, the DDA and the Government of NCT of  

Delhi and proceeded to observe:  

“The only  argument  made  was that  urgency was because  of  ensuing Common Wealth Games and since those have already  concluded, the urgency as seized to exist.   This is  a myopic  view  of  the  requirement  for  such  a  project.   No  doubt,  endeavour  was  to  establish  the  sub-station  before  the  Commonwealth Games, 2010 but that was not the only reason  for  urgency.   The  primary  reason  for  urgency  was,  and  continuous to be, that the substation in East Delhi is needed to  evacuate and utilize the power generated from 1500 MW Gas  based  Plant  at  Bawana  which  is  being  constructed.   The  urgency was, and continuous to exist, i.e. the need for adequate  power supply to the residents of this city.   This is an urgent  need keeping in view the wide gap between the demand and  supply.   No doubt,   the plans  were  to  commission  it  before  Common Wealth Games.  That has not happened also because  of the reason that stay was granted in these proceedings.  Be as  it  may,   it  cannot  be  argued  that  merely  because  Common  Wealth Games are over, the respondent authorities can now set  up the sub-station leisurely.  These are the aspects which are to  be  gone  into  by  the  Competent  Authority  while  exercising  powers under Section 17 (4) of the Act. Once it is seen that all  relevant  factors  were  taken  into   consideration  and  the  Competent  Authority  was  not  influenced  by  any  irrelevant  consideration or  the power  exercised was not   the  result  of  malafide,  the  subjective  satisfaction  of  the  Competent  Authority, based on those objective considerations namely the  purpose of invocation of urgency clause to acquire continued to  exist   the   Court  would  be  loathe  to  interfere  with  such  discretion  exercised  by  the  Competent  Authority  dispensing  

15

16

with  the enquiry under Section 5A of the Act.”

8. The Division Bench of the High Court then referred to the judgments of  

this  Court  in  First  Land  Acquisition  Collector  and  Others  v.  Nirodhi  

Prakash Ganguli  and Another,  (2002) 4 SCC  160; Union of India &  

Others v. Praveen Gupta and Others (1997) 9 SCC 78; Nand Kishore  

Gupta and Others v. State of U.P. and Others (2010) 10 SCC 282 and of  

the  High  Court  in  Bijwasan  Gram Vikas  Samiti  v.  Lt.  Governor  and  

Others – WP(C) No. 1307/2010, decided on 5.10.2010 and negatived the  

appellants’  challenge to the invoking of  Section 17 of the Act.    The  

Division  Bench  distinguished  the  judgments  relied  upon  by  the  

appellants’  counsel  by  observing  that  those  cases  did  not  involve  

challenge to the acquisition of land for infrastructure projects meant for  

larger public interest. At the same time, the Division Bench referred to  

the judgments in Rajiv Joshi  v. Union of India 2009 (159) DLT 214,  

Rajinder  Kishan  Gupta  and  another  v.  Lt.  Governor,  Government  of  

NCT of  Delhi  2010 (114)  DLT 708,  Sumit  Import  Services  Ltd.  and  

another v. Delhi Metro Rail Corporation and others 2008 (103) DRJ 263,  

M/s.  A.B.Tools  Ltd.  and  another  v.  Union  of  India  WP  (C)  

No.4611/1996, decided on 3.2.2010, Deepak Resorts v. Union of India  

2008 (149) DLT 582, Ajay Kumar Sanghi v. Delhi Police 2009 (163)  

16

17

DLT 74, Union of India and others v. Pramod Gupta (1997)  9 SCC 78,  

Sheikhar Hotels Gulmohar Enclave v. State of U.P. (2008) 14 SCC 716  

and Jai Narain v. Union of India (1999) 1 SCC 9 in which the acquisition  

of land for Airport, construction of metro station/metro line, installation  

of  LPG  Bottling  Plant,  construction  of  sewage  treatment  plant,  

construction of police station, relocation of timber merchants outside the  

walled city and widening of National Highway by invoking the urgency  

provisions contained in Section 17 of the Act was upheld by the High  

Court and this Court.

9. Learned counsel for the parties reiterated the arguments made before the  

High Court. While Shri Dhruv Mehta relied upon the judgments of this  

Court in Anand Singh v. State of U.P. (2010) 11 SCC 242 and Radhy  

Shyam  v.  State  of  U.P.  (2011)  5  SCC  553  to  emphasize  that  the  

acquisition of land for establishment of 400/220 KV sub-station did not  

warrant invoking of the urgency provisions contained in the Act because  

the proposal for establishment of the sub-station was initiated more than  

five yeas prior to the issue of notification under Section 4(1) read with  

Section 17(1) and (4) of the Act and there was no justification to deprive  

the appellants  of  the right  to  be heard before  being deprived of  their  

property, Shri P.P. Malhotra, learned Additional Solicitor General argued  

17

18

that the time consumed in the exchange of correspondence between the  

functionaries of the Government, the DTL and the DDA cannot be made  

a  ground  for  nullifying  the  exercise  of  the  State’s  power  of  eminent  

domain.   In  support  of  his  argument,  Shri  Malhotra  relied  upon  the  

judgments of Deepak Pahwa v. Lt. Governor of Delhi (1984) 4 SCC 308  

and Chameli  Singh v. State of U.P.  (1996) 2 SCC 549.  Shri  Waziri,  

learned  counsel  for  the  DTL,  supplemented  the  argument  of  learned  

Additional Solicitor General and submitted that the Court may not quash  

the acquisition of the appellants’ land because the work for establishing  

the sub-station has been completed to a large extent.  Learned counsel  

submitted that the appellants’ land cannot be left out because the same is  

needed for construction of project road.  Shri Waziri also submitted that  

the sub-station is required for evacuation of power which will be made  

available  from the Dadri  Power  Plant  and no other  suitable  land was  

available for the sub-station.

10. We have considered the respective arguments/submissions and carefully  

scrutinized the record including the documents made available during the  

course of  hearing.   The compulsory acquisition of  land has generated  

enormous litigation in the country in last more than five decades and this  

18

19

Court has been repeatedly called upon to adjudicate upon the legality of  

the notifications issued under the Act.  

11. In State of U.P. v. Pista Devi  (1986) 4 SCC 251, Rajasthan Housing  

Board v. Shri Kishan (1993) 2 SCC 84,  Jai Narain v. Union of India  

(supra),  Union of  India v.  Praveen Gupta (supra),    Land Acquisition  

Collector  v. Nirodhi Prakash Ganguli  (supra),   Anand Buttons Ltd. v.  

State of Haryana (2005) 9 SCC 164, Tika Ram v. State of U.P. (2009) 10  

SCC  689, Nand Kishore Gupta v. State of U.P. (2010) 10 SCC 282 and  

some other judgments,  the acquisition of land under Section 4(1) read  

with  Section  17(1)  and  17(4)  and some  of  the  State  amendments  for  

different public purposes, i.e., for construction of houses for poor and the  

members  of  reserved  categories,  establishment  of  medical  college,  

construction of sewage treatment plant under the Court’s order and for  

construction of Express Way has been approved.  As against this,  the  

acquisition  of  land by invoking the  urgency  provisions  for  the public  

purposes, like, planned residential, commercial, industrial or institutional  

development has been disapproved in Narayan Govind Gavate v. State of  

Maharashtra (1977) 1 SCC 133,  State of  Punjab v. Gurdial Singh (1980)  

2 SCC 471, Om Prakash v. State of U.P. (1998) 6 SCC 1, Union of India  

v. Mukesh Hans (2004) 8 SCC 14, Union of India v. Krishan Lal Arneja  

19

20

(2004) 8 SCC 453, Hindustan Petroleum Corpn. Ltd. v. Darius Shapur  

Chenai  (2005)  7  SCC 627,  Essco  Fabs  (P)  Ltd.  v.  State  of  Haryana  

(2009) 2 SCC 377, Babu Ram v. State  of  Haryana (2009) 10 SCC 115,  

Anand Singh v. State of U.P. (supra), Dev Sharan v. State of U.P.  (2011)  

4 SCC 769, State of West Bengal v.  Prafulla Churan Law (2011) 4 SCC  

537 , Radhy Shyam v. State of U.P. (supra) and Devender Kumar Tyagi  

v. State of U.P. (2011) 9 SCC 164 because the explanation given by the  

acquiring authority for invoking Section 17(1) and/or 17(4) was found to  

be  wholly  unsatisfactory  or  it  was  found  that  there  was  total  non-

application  of  mind  by  the  competent  authority  on  the  question  of  

necessity and desirability of invoking the urgency provisions.

12. Although, it  is neither possible nor desirable to lay down any straight  

jacket formula which can be applied to each and every case involving  

challenge to the acquisition of land by invoking the urgency provision, it  

will be profitable to notice two recent judgments in which several judicial  

precedents including some of the judgments referred to in the impugned  

order have been considered and some concrete propositions have been  

laid down which could supply guidance for deciding such matters.   In  

Anand Singh v. State of U.P. (supra), this Court considered the question  

whether  the  State  Government  could  invoke  Section  17(4)  for  the  

20

21

acquisition  of  land  for  a  residential  colony  to  be  constructed  by  

Gorakhpur  Development  Authority,  Gorakhpur.  After  noticing  factual  

matrix of the case and about 16 judgments, the Court held:  

“43. The exceptional and extraordinary power of doing away  with an enquiry under Section 5-A in a case where possession  of the land is required urgently or in an unforeseen emergency  is  provided  in  Section  17  of  the  Act.  Such  power  is  not  a  routine  power  and  save  circumstances  warranting  immediate  possession it  should not  be lightly  invoked. The guideline is  inbuilt in Section 17 itself for exercise of the exceptional power  in dispensing with enquiry under Section 5-A. Exceptional the  power,  the more circumspect  the Government  must  be in its  exercise. The Government obviously, therefore, has to apply its  mind before it dispenses with enquiry under Section 5-A on the  aspect  whether  the  urgency is  of  such a  nature that  justifies  elimination of summary enquiry under Section 5-A.

44. A repetition of the statutory phrase in the notification that  the State Government is satisfied that the land specified in the  notification is urgently needed and the provision contained in  Section  5-A  shall  not  apply,  though  may  initially  raise  a  presumption  in  favour  of  the  Government  that  prerequisite  conditions for exercise of such power have been satisfied, but  such  presumption  may  be  displaced  by  the  circumstances  themselves  having no reasonable  nexus  with the purpose for  which  the  power  has  been  exercised.  Upon  challenge  being  made to the use of power under Section 17, the Government  must  produce  appropriate  material  before  the  court  that  the  opinion for dispensing with the enquiry under Section 5-A has  been formed by the Government after due application of mind  on the material placed before it.

45. It is true that power conferred upon the Government under  Section 17 is administrative and its opinion is entitled to due  weight, but in a case where the opinion is formed regarding the  urgency based on considerations not germane to the purpose,  

21

22

the judicial review of such administrative decision may become  necessary.

46. As to in what circumstances the power of emergency can be  invoked  are  specified  in  Section  17(2)  but  circumstances  necessitating invocation of urgency under Section 17(1) are not  stated  in  the  provision  itself.  Generally  speaking,  the  development of an area (for residential purposes) or a planned  development  of  city,  takes  many  years  if  not  decades  and,  therefore,  there  is  no  reason  why  summary  enquiry  as  contemplated under Section 5-A may not be held and objections  of  landowners/persons  interested  may  not  be  considered.  In  many cases, on general assumption likely delay in completion  of  enquiry  under  Section  5-A  is  set  up  as  a  reason  for  invocation  of  extraordinary  power  in  dispensing  with  the  enquiry little realising that an important and valuable right of  the person interested in the land is being taken away and with  some effort enquiry could always be completed expeditiously.

47.  The  special  provision  has  been  made  in  Section  17  to  eliminate enquiry under Section 5-A in deserving and cases of  real  urgency.  The Government  has  to  apply  its  mind  on the  aspect  that  urgency  is  of  such  nature  that  necessitates  dispensation of enquiry under Section 5-A.  We have already  noticed a few decisions of this Court. There is a conflict of view  in the two decisions of this Court viz. Narayan Govind Gavate  and Pista Devi. In Om Prakash this Court held that the decision  in  Pista  Devi must  be confined to the fact  situation in those  days when it was rendered and the two-Judge Bench could not  have  laid  down  a  proposition  contrary  to  the  decision  in  Narayan Govind Gavate. We agree.

48.  As  regards  the  issue  whether  pre-notification  and  post- notification  delay  would  render  the  invocation  of  urgency  power void, again the case law is not consistent. The view of  this  Court  has  differed  on  this  aspect  due  to  different  fact  situation prevailing in those cases.  In our opinion such delay  will  have  material  bearing  on  the  question  of  invocation  of  urgency power, particularly in a situation where no material has  

22

23

been placed by the appropriate  Government  before  the court  justifying  that  urgency  was  of  such  nature  that  necessitated  elimination of enquiry under Section 5-A.”

13. In Radhy Shyam v. State of U.P. (supra), this Court considered challenge  

to the acquisition of land under Section 4(1) read with Section 17(1) and  

(4) for planned industrial development of District Gautam Budh Nagar by  

Greater Noida Industrial Development Authority and extensively referred  

to  the  judgment  in  Narayan  Govind  Gavate  v.  State  of  Maharashtra  

(1977) 1 SCC 133 and also adverted to other judgments, in which the  

importance of the rules of natural justice has been highlighted, and culled  

out the following principles:  

“(i) Eminent domain is a right inherent in every sovereign to  take and appropriate property belonging to citizens for public  use. To put it differently, the sovereign is entitled to reassert its  dominion over any portion of  the soil  of  the State  including  private property without its owner's consent provided that such  assertion is on account of public exigency and for public good –  Dwarkadas  Shrinivas v.  Sholapur  Spg.  and  Wvg.  Co.  Ltd.,  Charanjit  Lal  Chowdhury v.  Union  of  India and  Jilubhai  Nanbhai Khachar v. State of Gujarat.

(ii) The legislations which provide for compulsory acquisition  of  private  property  by  the  State  fall  in  the  category  of  expropriatory legislation and such legislation must be construed  strictly – DLF Qutab Enclave Complex Educational Charitable  Trust v.  State  of  Haryana;  State  of  Maharashtra v.  B.E.  Billimoria and Dev Sharan v. State of U.P.

23

24

(iii) Though, in exercise of the power of eminent domain, the  Government  can  acquire  the  private  property  for  public  purpose, it must be remembered that compulsory taking of one's  property  is  a  serious  matter.  If  the  property  belongs  to  economically disadvantaged segment of the society or people  suffering  from  other  handicaps,  then  the  court  is  not  only  entitled but  is  duty-bound to scrutinise the action/decision of  the  State  with  greater  vigilance,  care  and  circumspection  keeping in view the fact that the landowner is likely to become  landless  and  deprived  of  the  only  source  of  his  livelihood  and/or shelter.

(iv) The property of a citizen cannot be acquired by the State  and/or  its  agencies/instrumentalities  without  complying  with  the  mandate  of  Sections  4,  5-A and  6  of  the  Act.  A  public  purpose, however laudable it may be does not entitle the State  to  invoke the urgency provisions  because  the same have the  effect of depriving the owner of his right to property without  being  heard.  Only  in  a  case  of  real  urgency,  can  the  State  invoke  the  urgency  provisions  and  dispense  with  the  requirement  of  hearing  the  landowner  or  other  interested  persons.

(v) Section 17(1) read with Section 17(4) confers extraordinary  power  upon  the  State  to  acquire  private  property  without  complying with the mandate of Section 5-A. These provisions  can be invoked only when the purpose of  acquisition cannot  brook the  delay  of  even a  few weeks or  months.  Therefore,  before excluding the application of Section 5-A, the authority  concerned must  be fully  satisfied  that  time of few weeks or  months likely to be taken in conducting inquiry under Section  5-A will,  in  all  probability,  frustrate  the  public  purpose  for  which land is proposed to be acquired.

(vi) The satisfaction of the Government on the issue of urgency  is  subjective  but  is  a  condition  precedent  to  the  exercise  of  power under Section 17(1) and the same can be challenged on  the ground that the purpose for which the private property is  sought to be acquired is not a public purpose at all or that the  

24

25

exercise  of  power  is  vitiated  due  to  mala  fides  or  that  the  authorities concerned did not apply their mind to the relevant  factors and the records.

(vii) The exercise of power by the Government under Section  17(1) does not necessarily result in exclusion of Section 5-A of  the Act in terms of which any person interested in land can file  objection and is entitled to be heard in support of his objection.  The use of word “may” in sub-section (4) of Section 17 makes  it clear that it merely enables the Government to direct that the  provisions of Section 5-A would not apply to the cases covered  under  sub-section  (1)  or  (2)  of  Section  17.  In  other  words,  invoking of Section 17(4) is not a necessary concomitant of the  exercise of power under Section 17(1).

(viii)  The  acquisition  of  land  for  residential,  commercial,  industrial  or  institutional  purposes  can  be  treated  as  an  acquisition for public purposes within the meaning of Section 4  but that, by itself, does not justify the exercise of power by the  Government under Sections 17(1) and/or 17(4). The court can  take  judicial  notice  of  the  fact  that  planning,  execution  and  implementation  of  the  schemes  relating  to  development  of  residential, commercial, industrial or institutional areas usually  take  few  years.  Therefore,  the  private  property  cannot  be  acquired for such purpose by invoking the urgency provision  contained in Section 17(1). In any case, exclusion of the rule of  audi alteram partem embodied in Sections 5-A(1) and (2) is not  at all warranted in such matters.

(ix) If land is acquired for the benefit of private persons, the  court should view the invoking of Sections 17(1) and/or 17(4)  with  suspicion  and  carefully  scrutinise  the  relevant  record  before adjudicating upon the legality of such acquisition.”

14. What needs to be emphasized is that although in exercise of the power of  

eminent  domain,  the State can acquire  the private  property for  public  

25

26

purpose,  it  must  be  remembered  that  compulsory  acquisition  of  the  

property belonging to a private individual  is  a serious matter  and has  

grave repercussions on his Constitutional right of not being deprived of  

his property without the sanction of law – Article 300A and the legal  

rights. Therefore, the State must exercise this power with great care and  

circumspection.  At  times,  compulsory  acquisition  of  land  is  likely  to  

make the owner landless. The degree of care required to be taken by the  

State is greater when the power of compulsory acquisition of private land  

is exercised by invoking the provisions like the one contained in Section  

17 of the Act because that results in depriving the owner of his property  

without being afforded an opportunity of hearing.

15. In  the  light  of  the  above,  it  is  to  be  seen  whether  there  was  any  

justification for invoking the urgency provisions contained in Section 17  

(1) and (4) of the Act for the acquisition of the appellants’ land.  The  

Division Bench of the High Court accepted the explanation given by the  

respondents  by  observing that  sub-station  in  East  Delhi  is  needed to  

evacuate and utilize the power generated from 1500 MW gas based plant  

at Bawana.  While doing so the Bench completely overlooked that there  

was  long  time  gap  of  more  than  five  years  between  initiation  of  the  

proposal for establishment of the sub-station and the issue of notification  

26

27

under Section 4 (1) read with Section 17 (1) and (4) of the Act.  The High  

Court also failed to notice that the Government of NCT of Delhi had not  

produced  any  material  to  justify  its  decision  to  dispense  with  the  

application of Section 5A of the Act. The documents produced by the  

parties  including  the  notings  recorded  in  file  bearing  No.  

F.S(11)/08/L&B/LA  and  the  approval  accorded  by  the  Lieutenant  

Governor do not contain anything from which it can be inferred that a  

conscious decision was taken to dispense with the application of Section  

5A which represents two facets of the rule of hearing that is the right of  

the land owner to file objection against the proposed acquisition of land  

and  of  being  heard  in  the  inquiry  required  to  be  conducted  by  the  

Collector.  

16. The  scope  of  the  rule  of  hearing,  i.e.,  audi  alteram  partem  was  

highlighted by the three-Judge Bench in  Sayeedur Rehman v.  State of  

Bihar (1973) 3 SCC 333  in the following words:  

“11. … This unwritten right of hearing is fundamental to a just  decision by any authority which decides a controversial issue  affecting the rights of the rival contestants.  This right has its  roots in the notion of fair procedure. It draws the attention of  the  party concerned  to  the  imperative  necessity  of  not  overlooking  the  other  side  of  the  case  before  coming  to  its  decision, for nothing is more likely to conduce to just and right  

27

28

decision  than  the  practice  of  giving  hearing  to  the  affected  parties.

17. In  Maneka Gandhi v.  Union of India (1978) 1 SCC 248 Bhagwati,  J.  

speaking for himself and Untwalia and Fazal Ali, JJ. observed:  

“14.  …  The  audi  alteram  partem  rule  is  intended  to  inject  justice into the law and it cannot be applied to defeat the ends  of justice, or to make the law ‘lifeless, absurd, stultifying, self- defeating  or  plainly  contrary  to  the  common  sense  of  the  situation’. Since the life of the law is not logic but experience  and every legal proposition must,  in the ultimate analysis,  be  tested on the touchstone of pragmatic realism, the audi alteram  partem  rule  would,  by  the  experiential  test,  be  excluded,  if  importing the right to be heard has the effect of paralysing the  administrative  process  or  the  need  for  promptitude  or  the  urgency of the situation so demands.  But at the same time it   must be remembered that this is a rule of vital importance in   the field of administrative law and it must not be jettisoned save   in very exceptional circumstances where compulsive necessity   so demands. It is a wholesome rule designed to secure the rule   of law and the court should not be too ready to eschew it in its   application to a given case. True it is that in questions of this  kind a fanatical or doctrinaire approach should be avoided, but  that  does  not  mean  that  merely  because  the  traditional  methodology of a formalised  hearing may have the effect  of  stultifying the exercise of the statutory power, the audi alteram  partem should be wholly excluded. The Court must make every   effort  to  salvage  this  cardinal  rule  to  the  maximum  extent   permissible  in  a  given  case.  It  must  not  be  forgotten  that   ‘natural  justice  is  pragmatically  flexible  and is  amenable  to   capsulation under the compulsive pressure of circumstances’.   The audi alteram partem rule is not cast in a rigid mould and   judicial  decisions  establish  that  it  may  suffer  situational   modifications. The core of it  must,  however,  remain, namely,   that the person affected must have a reasonable opportunity of   being heard and the hearing must be a genuine hearing and not   an empty public relations exercise.”

28

29

(emphasis supplied)

18. In  Mohinder  Singh Gill v.  Chief  Election Commr.(1978)  1 SCC 405,  

Krishna  Iyer,  J.  speaking  for  himself,  Beg,  C.J.  and  Bhagwati,  J.  

observed as under:  

“43. Indeed, natural justice is a pervasive facet of secular law  where a spiritual touch enlivens legislation, administration and  adjudication,  to  make  fairness  a  creed  of  life.  It  has  many  colours and shades,  many forms and shapes and, save where  valid law excludes it, applies when people are affected by acts  of authority. It is the hone of healthy Government, recognised  from earliest times and not a mystic testament of Judge-made  law.  Indeed,  from  the  legendary  days  of  Adam—and  of  Kautilya's Arthashastra—the rule of law has had this stamp of  natural justice which makes it social justice. We need not go  into these deeps for the present except to indicate that the roots  of natural justice and its foliage are noble and not new-fangled.  Today its application must be sustained by current legislation,  case  law  or  other  extant  principle,  not  the  hoary  chords  of  legend  and  history.  Our  jurisprudence  has  sanctioned  its  prevalence even like the Anglo-American system.”

“48.  Once we understand the soul of the rule as fair play in  action—and it is so—we must hold that it extends to both the  fields. After all, administrative power in a democratic set-up is  not  allergic  to  fairness  in  action  and  discretionary  executive  justice cannot degenerate into unilateral injustice. Nor is there  ground to be frightened of delay, inconvenience and expense, if  natural  justice  gains  access.  For  fairness  itself  is  a  flexible,  pragmatic  and  relative  concept,  not  a  rigid,  ritualistic  or  sophisticated abstraction. It is not a bull in a china shop, nor a  bee in one's bonnet. Its essence is good conscience in a given  situation: nothing more—but nothing less. The ‘exceptions’ to  the rules of natural justice are a misnomer or rather are but a  shorthand form of expressing the idea that in those exclusionary  cases  nothing  unfair  can  be  inferred  by  not  affording  an  

29

30

opportunity to present or meet a case. Textbook excerpts and  ratios from rulings can be heaped, but they all converge to the  same point that audi alteram partem is the justice of the law,  without, of course, making law lifeless, absurd, stultifying, self- defeating  or  plainly  contrary  to  the  common  sense  of  the  situation.”

19. In  Swadeshi Cotton  Mills v.  Union  of  India  (1981)  1  SCC  664 the  

majority  of  the  three-Judge Bench  held that  the rule  of  audi  alteram  

partem must  be  complied  with  even  when  the  Government  exercises  

power  under  Section  18-AA  of  the  Industries  (Development  and  

Regulation)  Act,  1951  which  empowers  the  Central  Government  to  

authorise  taking  over  of  the  management  of  industrial  undertaking.  

Sarkaria,  J.  speaking  for  himself  and  Desai,  J.  referred  to  the  

development of law relating to applicability of the rule of  audi alteram  

partem to  administrative  actions,  noticed  the  judgments  in  Ridge v.  

Baldwin (1964) AC 40,  A.K. Kraipak v.  Union of India (1969) 2 SCC  

262,  Mohinder  Singh Gill v.  Chief  Election Commr.  (supra),  Maneka  

Gandhi v. Union of India (supra) and State of Orissa v. Dr. Binapani Dei  

(1967)  2  SCR  625 and  quashed  the  order  passed  by  the  Central  

Government  for  taking  over  the  management  of  the  industrial  

undertaking of the appellant on the ground that opportunity of hearing  

has not been given to the owner of the undertaking and remanded the  

30

31

matter  for  fresh  consideration  and  compliance  with  the  rule  of  audi  

alteram partem.

20. In  Munshi Singh v.  Union of India (1973) 2 SCC 337, the three-Judge  

Bench of this Court emphasised the importance of Section 5-A in the  

following words:  

“7. … Sub-section (2) of Section 5-A makes it obligatory on the  Collector  to  give  an  objector  an  opportunity  of  being heard.  After hearing all objections and making further inquiry he is to  make  a  report  to  the  appropriate  Government  containing  his  recommendation  on  the  objections.  The  decision  of  the  appropriate  Government  on  the  objections  is  then final.  The  declaration under Section 6 has to be made after the appropriate  Government is satisfied, on a consideration of the report, if any,  made  by the  Collector  under  Section 5-A(2).  The legislature  has,  therefore,  made  complete  provisions  for  the  persons  interested to file objections against the proposed acquisition and  for the disposal of their objections. It is only in cases of urgency  that  special  powers  have  been  conferred  on  the  appropriate  Government to dispense with the provisions of Section 5-A.”

21. It is also apposite to mention that no tangible evidence was produced by  

the respondents before the Court to show that the task of establishing the  

sub-station at Mandoli was required to be accomplished within a fixed  

schedule and the urgency was such that even few months time, which  

may have been consumed in the filing of objections by the land owners  

and other interested persons under Section 5A(1) and holding of inquiry  

by the Collector under Section 5A(2), would have frustrated the project.  

31

32

It seems that the Bench of the High Court was unduly influenced by the  

fact that consumption of power in Delhi was increasing everyday and the  

DTL was making an effort to ensure supply of power to different areas  

and for that purpose establishment of sub-station at village Mandoli was  

absolutely imperative.  In our view, the High Court was not justified in  

rejecting the appellants’ challenge to the invoking of urgency provisions  

on the premise that the land was required for implementation of a project  

which would benefit large section of the society. It needs no emphasis  

that majority of the projects undertaken by the State and its agencies /  

instrumentalities,  the implementation  of  which requires  public  money,  

are meant to benefit the people at large or substantially large segment of  

the society.  If what the High Court has observed is treated as a correct  

statement of law, then in all such cases the acquiring authority will be  

justified in invoking Section 17 of the Act and dispense with the inquiry  

contemplated  under  Section  5A,  which  would  necessarily  result  in  

depriving  the  owner  of  his  property  without  any  opportunity  to  raise  

legitimate objection. However, as has been repeatedly held by this Court,  

the invoking of the urgency provisions can be justified only if there exists  

real emergency which cannot brook delay of even few weeks or months.  

In other words, the urgency provisions can be invoked only if even small  

32

33

delay of few weeks or months may frustrate the public purpose for which  

the land is sought to be acquired.  Nobody can contest that the purpose  

for which the appellants’ land and land belonging to others was sought to  

be acquired was a public purpose but it is one thing to say that the State  

and its instrumentality wants to execute a project of public importance  

without loss of time and it is an altogether different thing to say that for  

execution of such project, private individuals should be deprived of their  

property without even being heard.  It appears that attention of the High  

Court  was  not  drawn to  the  following  observations  made  in  State  of  

Punjab v. Gurdial Singh (supra):  

“it  is  fundamental  that  compulsory  taking  of  a  man's  property is a serious matter and the smaller the man the  more serious the matter.  Hearing him before depriving  him is both reasonable and pre-emptive of arbitrariness,  and denial of this administrative fairness is constitutional  anathema except for good reasons. Save in real urgency  where public interest does not brook even the minimum  time needed to give a hearing land acquisition authorities  should not, having regard to Articles 14 (and 19), burke  an  enquiry  under  Section  17  of  the  Act.  Here  a  slumbering  process,  pending  for  years  and  suddenly  exciting  itself  into  immediate  forcible  taking,  makes  a  travesty of emergency power.”

22. A recapitulation of  the facts  would show that  the idea of  establishing  

400/220 KV sub-station  was  mooted  prior  to  August,  2004.  For  next  

almost  three  years,  the  officers  of  the  DTL and the  DDA exchanged  

33

34

letters on the issue of allotment of land. On 28.7.2008 Secretary (Power),  

Government of NCT of Delhi-cum-CMD, DTL made a suggestion for the  

acquisition of land by invoking Section 17 of the Act. This became a tool  

in the hands of the concerned authorities and the Lieutenant Governor  

mechanically approved the proposal contained in the file without trying  

to find out as to why the urgency provisions were being invoked after a  

time  gap  of  five  years.  If  the  sub-station  was  to  be  established  on  

emergency basis, the authorities of the DTL would not have waited for  

five years for the invoking of urgency provisions enshrined in the Act.  

They would have immediately approached the Government of NCT of  

Delhi and made a request that land be acquired by invoking Section 17 of  

the Act. However, the fact of the matter is that the concerned officers /  

functionaries of the DTL, the DDA and the Government of NCT of Delhi  

leisurely dealt with the matter for over five years. Even after some sign of  

emergency was indicated in letter dated 9.9.2008 of the Joint Secretary  

(Power), who made a mention of the Commonwealth Games scheduled  

to be organised in October, 2010, it took more than one year and two  

months to the competent authority to issue the preliminary notification.  

Therefore, we are unable to approve the view taken by the High Court on  

34

35

the sustainability of the appellants’ challenge to the acquisition of their  

land.

23. Before concluding we deem it appropriate to notice the judgments relied  

upon  by the learned Additional Solicitor General. A cursory reading of  

the judgment in Deepak Pahwa v. Lt. Governor of Delhi (supra) (3-Judge  

Bench)  gives  an  impression  that  the  proposition  contained  therein  

supports the argument of Shri Malhotra, that pre-notification delay is not  

relevant  for  deciding  legality  of  the  exercise  of  the  State’s  power  of  

eminent domain and invoking of the urgency provisions contained in the  

Act  but  careful  reading  of  the  judgment  along  with  the  precedents  

referred to in paragraph 8 makes it clear that nothing contained therein  

can be relied upon for overlooking the time gap of five years between the  

initiation of proposal for establishment of the sub-station and the issue of  

notification under Section 4(1) read with Section 17 (1) and (4) of the  

Act.  That  case  involved  challenge  to  the  acquisition  of  land  for  

construction of  ‘New Transmitting Station for  the Delhi  Airport’.  The  

High  Court  dismissed  the  writ  petition  in  limine.  The  special  leave  

petition  was  also  dismissed  at  the  threshold.  While  dealing  with  the  

argument that there was no justification to invoke Section 17(4) of the  

Act  and to dispense  with the inquiry under  Section 5A because  eight  

35

36

years  time  was  spent  in  inter-departmental  discussions,  this  court  

observed:  

“The other ground of attack is that if regard is had to the  considerable length of time spent on inter-departmental  discussion before the notification under Section 4(1) was  published,  it  would  be  apparent  that  there  was  no  justification  for  invoking  the  urgency  clause  under  Section  17(4)  and  dispensing  with  the  enquiry  under  Section 5-A. We are afraid,  we cannot agree with this  contention.  Very  often  persons  interested  in  the  land  proposed to be acquired make various representations to  the  concerned  authorities  against  the  proposed  acquisition.  This is bound to result  in a multiplicity of  enquiries,  communications  and  discussions  leading  invariably  to  delay  in  the  execution  of  even  urgent  projects. Very often the delay makes the problem more  and more acute and increases the urgency of the necessity  for acquisition. It is, therefore, not possible to agree with  the  submission  that  mere  pre-notification  delay  would  render the invocation of the urgency provisions void. We  however  wish  to  say  nothing  about  post-notification  delay. In  Jage Ram v.  State of Haryana (1971) 1 SCC  671 this  Court  pointed  out  the  fact  that  the  State  Government or the party concerned was lethargic at an  earlier stage is not very relevant for deciding the question  whether on the date on which the notification was issued,  there  was  urgency  or  not.  In  Kasireddy  Papaiah v.  Government of Andhra Pradesh, AIR 1975 AP 269 it was  held, “… delay on the part of tardy officials to take the  further action in the matter of acquisition is not sufficient  to nullify the urgency which existed at the time of the  issue of the notification and to hold that there was never  any urgency”. In the result both the submissions of the  learned counsel  for  the petitioners are rejected and the  special leave petitions are dismissed.”

(underlining is ours)

36

37

In making the aforesaid observation, the Court appears to have been unduly  

influenced by what was perceived at the relevant time as pulling of strings in  

the power corridors by the interested persons which resulted in frustration of the  

public  oriented projects.  The general  observations made in  Deepak Pahwa’s  

case cannot supply basis for approving the impugned order and the notifications  

challenged  by  the  appellants  because  it  is  neither  the  pleaded  case  of  the  

respondents  nor it  has been suggested that  the delay was caused due to the  

representation made by the appellants or that they brought extraneous pressure  

to prevent the acquisition of their land.  

24. We may now notice the two decisions referred to in paragraph 8 of the  

judgment  in  Deepak  Pahwa’s  case.  In  Jage  Ram v.  State  of  Haryana  

(1971) 1 SCC 671 the acquisition of land for setting up a factory for the  

manufacture of China-ware, Porcelain-ware including wall glazed tiles,  

etc., at the instance of a private industrialist by invoking Section 17(2)(c)  

of  the Act (as amended by Haryana Legislature)  was challenged.  The  

State  Government  had  issued  notification  dated  14/17.03.1969  under  

Section 4 of the Act. Simultaneously, a direction was given for taking  

action under Section 17(2)(c) and it was declared that the provisions of  

Section 5A shall not apply. On 8.4.1969 the appellants filed writ petition,  

which  was  dismissed  by  the  High  Court.  This  Court  negatived  the  

37

38

challenge  to  the  invoking  of  the  urgency  provisions  by  making  the  

following observations:  

“The allegations in the writ petition include the assertion  that there was no urgency in the matter of acquiring the  land in question and therefore there was no justification  for having recourse to Section 17 and thus deprive the  appellants of the benefit of Section 5-A of the Act. It was  further  alleged  therein  that  the  acquisition  in  question  was  made  for  the  benefit  of  a  company  and  hence  proceedings should have been taken under Sections 38 to  44(B) of the Act and that there was no public purpose  involved in the case. It was further pleaded that the land  acquired was not waste and arable land and that Section  2(c) of the Act did not confer power on the Government  to dispense with the proceedings under Section 5-A. In  the  counter-affidavit  filed  by  the  Deputy  Director  of  Industries (Administration), Government of Haryana on  behalf  of  the  State  of  Haryana,  the  above  allegations  were all denied. Therein it is stated that at the instance of  the State of Haryana, Government of India had issued a  letter of intent to a company for setting up a factory for  the manufacture of Glazed Tiles  etc. in village Kasser.  That project was to be started with the collaboration of a  foreign  company  known  as  Pilkington  Tiles  Ltd.  The  scheme for setting up the project had been finalised and  approved by the concerned authorities. On November 26,  1968, the Government wrote to one of the promoters of  the project, Shri H.L. Somany asking him to complete the  “arrangements  for  the import  of  capital  equipment  and  acquisition of land in Haryana State for setting up of the  proposed  factory”.  It  was  further  stated  in  that  communication  that  the  Government  was  pleased  to  extend the time for completing the project up to April 30,  1969.  Under  those  circumstances  it  had  become  necessary  for  the  State  of  Haryana  to  take  immediate  steps  to  acquire  the  required  land.  It  was  under  those  circumstances the Government was constrained to have  recourse  to  Section  17  of  the  Act.  The  Government  

38

39

denied the allegation that the facts of this case did not  come within the scope of Section 17(2)(c). It was also  denied that the acquisition in question was not made for a  public purpose.

There  is  no  denying  the  fact  that  starting  of  a  new  industry is in public interest. It is stated in the affidavit  filed  on  behalf  of  the  State  Government  that  the  new  State  of  Haryana  was  lacking  in  industries  and  consequently  it  had  become  difficult  to  tackle  the  problem of unemployment. There is also no denying the  fact  that  the  industrialisation  of  an  area  is  in  public  interest. That apart, the question whether the starting of  an  industry  is  in  public  interest  or  not  is  essentially  a  question that has to be decided by the Government. That  is  a  socio-economic  question.  This  Court  is  not  in  a  position  to  go  into  that  question.  So  long  as  it  is  not  established that the acquisition is sought to be made for  some  collateral  purpose,  the  declaration  of  the  Government that it is made for a public purpose is not  open to challenge. Section 6(3) says that the declaration  of the Government that the acquisition made is for public  purpose  shall  be  conclusive  evidence  that  the  land  is  needed for a public purpose. Unless it is shown that there  was a colourable exercise of power, it is not open to this  Court to go behind that declaration and find out whether  in a particular case the purpose for which the land was  needed was a public purpose or not: see Smt Somavanti  v. State of Punjab and Raja Anand Brahma Shah v. State  of U.P. On the facts of this case there can be hardly any  doubt that the purpose for which the land was acquired is  a public purpose.

Now coming to the question of urgency, it is clear from  the  facts  set  out  earlier  that  there  was  urgency.  The  Government of India was pleased to extend time for the  completion of the project up to April 30, 1969. Therefore  urgent  steps  had  to  be  taken  for  pushing  through  the  project. The fact that the State Government or the party  

39

40

concerned was lethargic  at  an earlier  stage is  not  very  relevant for deciding the question whether on the date on  which the notification was issued, there was urgency or  not. The conclusion of the Government in a given case  that  there  was  urgency  is  entitled  to  weight,  if  not  conclusive.”

There is nothing in the aforesaid judgment which can possibly support the cause  

of the respondents. The scheme for setting up an industry by a company known  

as  Pilkington  Tiles  Ltd.  of  which  one  H.S.  Somany  was  a  promoter  was  

finalized on 26.11.1968 and the notification was issued on 14/17.3.1969. This  

shows that the time gap between finalization of the scheme and the issue of  

preliminary notification was less than four months. Therefore, the judgment in  

Jage Ram’s case could not have been relied upon for taking the view that pre-

notification delay cannot be considered while deciding legality of the State’s  

action to invoke the urgency provisions. That apart, we have serious reservation  

whether the Court could have approved the invoking of urgency provisions for  

the acquisition of land on behalf of a private company ignoring that there is a  

separate Chapter for such acquisition.  

25. In Kasireddy Papaiah v. Government of A.P. AIR 1975 AP 269 to which  

reference has been made in the judgment of  Deepak Pahwa’s case, the  

learned Single Judge (Chinnappa Reddy, J., as he then was) rejected the  

challenge to the acquisition of land under Section 4(1) read with Section  

40

41

17(4). The facts of that case show that notification under Section 4(1)  

read with Section 17(4) was issued on 19.5.1970 and was published in  

the official gazette dated 24.9.1970. The declaration under Section 6 was  

published in official gazette dated 25.2.1971. The writ petition was filed  

on 16.9.1971. The High Court held that the time gap of six months was  

not fatal to the invoking of the urgency provisions because the land was  

acquired for providing house sites to the Harijans. There is nothing in  

that judgment which merits serious consideration by this Court.

26. In Chameli Singh v. State of U.P. (supra) this Court simply followed the  

observations made by the learned Single Judge of the Andhra Pradesh  

High Court in Kasireddy Papaiah’s case and held that the acquisition of  

land  for  providing  housing  accommodation for  Harijans  did  warrant  

invoking of the urgency provisions and delay by the officials cannot be  

made a ground to nullify the acquisition. There is no particular discussion  

in  the  judgment  about  the  time  lag  between  the  proposal  for  the  

acquisition of land and the issue of notification under Section 4(1) read  

with  Section  17(1)  and  (4).  Therefore,  that  judgment  is  also  of  no  

assistance to the respondents.  

41

42

27. It is also appropriate to mention that in paragraph 48 of the judgment in  

Anand Singh v. State of UP (supra) this Court did take cognizance of the  

conflicting views expressed on the effect  of  pre-notification and post-

notification delay on the invoking of urgency provisions and observed  

that such delay will have material bearing on the question of invocation  

of  urgency  power,  particularly,  when  no  material  is  produced  by  the  

appropriate Government to justify elimination of the inquiry envisaged  

under Section 5A.

28. In the result, the appeal is allowed and the impugned order is set aside.  

As a corollary, the writ petition filed by the appellants is allowed and the  

acquisition of their land is quashed. However, it is made clear that this  

judgment shall not preclude the competent authority from issuing fresh  

notification under Section 4(1) and taking other steps necessary for the  

acquisition  of  the  appellant’s  land.  If  the  respondents  initiate  fresh  

proceedings for the acquisition of the appellants’ land then they shall be  

free to file objections under Section 5A(1) and they shall also be entitled  

to be heard in the inquiry to be conducted by the Collector in terms of  

Section 5A(2) of the Act. The parties are left to bear their own costs.

……………………………………J.                    [G.S. Singhvi]

42

43

……………………………………J.        [Sudhansu Jyoti Mukhopadhaya]

New Delhi January 3, 2012.

43