CHANDIGARH HOUSING BOARD Vs M/S. PARASVANATH DEVELOPERS PVT. LTD.
Bench: HON'BLE MR. JUSTICE MOHAN M. SHANTANAGOUDAR, HON'BLE MR. JUSTICE R. SUBHASH REDDY
Judgment by: HON'BLE MR. JUSTICE MOHAN M. SHANTANAGOUDAR
Case number: C.A. No.-010748-010748 / 2016
Diary number: 32139 / 2016
Advocates: RACHANA JOSHI ISSAR Vs
JAY KISHOR SINGH
1
REPORTABLE
IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 10748 OF 2016
Chandigarh Housing Board ...Appellant
Versus
M/s. Parasvanath Developers Pvt. Ltd. & Anr …Respondents
J U D G M E N T
MOHAN M. SHANTANAGOUDAR, J.
1. Delay condoned in filing appeal.
2 This appeal arises out of the final order dated 11.05.2016
passed by the National Consumer Disputes Redressal
Commission at New Delhi (hereinafter ‘National Commission’)
in Consumer Complaint (C.C.) No. 19 of 2011, vide which the
Respondent No.1 and Appellant herein were directed to pay
Respondent No. 2 herein a principal sum of Rs. 1,03,31,250/-
with interest @ 10% p.a., Rs.1,00,000 for mental harassment
2
and agony, and Rs.1,00,000 towards litigation costs in the ratio
of 70:30.
3. The factual background to this appeal is as follows:
3.1 The Appellant herein, Chandigarh Housing Board
(hereinafter ‘CHB’) invited bids to implement an integrated
project with residential, commercial, and other related
infrastructure facilities at the Rajiv Gandhi Chandigarh
Technological Park in Chandigarh. The bid sent by Respondent
No. 1 herein, M/s. Parasvanath Developers Ltd. (hereinafter
‘Developer’) was accepted by CHB. Consequently, CHB and the
Developer entered into a Development Agreement dated
06.10.2006 for the grant of development rights in respect of
land measuring 123 acres. The said land was allotted to the
Developer by CHB for constructing residential units, who then
advertised its project for the sale of flats and pent houses as
“Parsvanath Pride Asia”.
3.2 Respondent No. 2 herein (hereinafter ‘the Complainant’)
applied for the allotment of a five-bedroom apartment in this
project and paid a sum of Rs.1,03,31,250/- towards the total
tentative price of Rs. 3,93,25,000/-. Later, a tripartite flat buyer
agreement (hereinafter ‘Tripartite Agreement’) was executed
3
between the Developer, CHB, and the Complainant on
23.04.2008. Clause 9(a) of this agreement stated that the
construction of the flat was likely to be completed within a
period of 36 months from the signing of the Development
Agreement between CHB and the Developer, i.e., 06.10.2006.
3.3 Having received no intimation from the Developer about
the status of the project, between September-October 2009,
the Complainant inquired and found that construction had not
been commenced at the project site. Consequently, he sought
a refund of the deposit amount of Rs.1,03,31,250 with interest
at 20% p.a. When the refund was not made, the Complainant
approached the National Commission on 24.02.2011. It is
crucial to note here that similar complaints were filed by other
flat buyers before the State Commission and the National
Commission.
3.4 Before the National Commission, it was the case of the
Developer that the construction could not be carried out in
time, as CHB had failed to hand over the possession of
unencumbered land to it for raising the construction. On the
contrary, CHB argued that disputes only existed for land
earmarked for commercial activities, and there was no dispute
4
with respect to the 123 acres of land handed over to the
Developer for the construction of residential units. Therefore, it
was contended by CHB that the Developer was liable to satisfy
the claim of the flat buyer and the complaint was bad as
against CHB for misjoinder of party. Notably, the dispute
between the Developer and the CHB with respect to the
Development Agreement was referred to arbitration.
3.5 Pending the arbitration proceedings, the National
Commission passed an order in a similar matter on 05.03.2013,
noting that the flat buyers could not be deprived of their
legitimate claims due to an inter se dispute between CHB and
the Developer. Observing that the Developer had failed to
construct the residential units and hand over possession in
time, the National Commission passed an interim order
directing the Developer to pay compensation to the flat buyer
in terms of Clause 9(c) of the Tripartite Agreement at Rs.
107.60 per sq metre, subject to the final outcome of the
arbitration proceedings. Further, in terms of Clause 9(d) of the
Tripartite Agreement, the Developer and CHB were directed to
pay interest at the uniform rate of 9% p.a. on the amount to be
refunded to the flat buyers in the ratio of 70:30.
5
3.6 Finally, on 09.01.2015, the learned arbitrator passed an
award in the arbitration proceedings between CHB and the
Developer. The award specifically noted that since the flat
buyers were not party to the arbitration, the award would only
bind CHB and the Developer, and the entitlement of the
residential flat buyers would have to be decided based on the
facts of each case in independent proceedings. However, with
respect to the liability to refund the advances collected from
the residential unit buyers, the learned arbitrator found that the
non-completion of the project was a result of breaches
committed by both, the Developer and CHB. Therefore, he
directed that any amount payable on account of refund of
price, interest, or compensation (if and when finally determined
by the National Commission or the Supreme Court) would be
borne by the Developer and CHB in the ratio of 70:30.
3.7 Meanwhile, an order was passed by a 3-judge Bench of
this Court on 21.04.2015 in an SLP filed against the order of the
National Commission dated 05.03.2013 and other connected
matters. Dismissing the SLP, the Court took note of the
arbitration award dated 09.01.2015 and observed that Clause
9(c) of the Tripartite Agreement, which stipulates the payment
6
of compensation, would only be applicable as against the
Developer if it is not in a position to offer a flat to the buyer
after the expiry of 36 months as stated in Clause 9(a) of the
Tripartite Agreement.
3.8 Finally, vide the impugned order dated 11.05.2016, the
National Commission disposed of the consumer complaint filed
by Respondent No. 2 herein. Taking into account the
observations in the final arbitral award attributing responsibility
of breach of the Development Agreement to the Developer and
CHB, as well as the fact that the Developer had received the
deposit sum from the Complainant long ago and had benefited
from it, the National Commission directed CHB and the
Developer to pay the principal sum of Rs. 1,03,31,250/- to the
Complainant at 10% p.a. from the date of deposit till
realization. Further, Rs. 1 lakh was awarded for mental
harassment and another Rs. 1 lakh was awarded towards
litigation charges. Both of these were directed to be borne by
the Developer and CHB in the ratio of 70:30. The instant appeal
has been preferred by CHB against this order, contesting the
liability fixed upon it with respect to the payment for litigation
7
costs and mental harassment, as well as the enhancement in
interest rate.
4. Heard learned Counsel for the parties.
5. Learned Counsel for the Appellant (CHB) submitted that
the impugned order is liable to be set aside as it wrongly
saddles CHB with the liability to pay the Complainant 30% of
the amount due towards mental harassment and litigation
costs. It is argued that such amount is in the nature of
compensation and must therefore be borne by the Developer
as Clause 9(c) of the Tripartite Agreement provides that the
Developer shall be liable to pay compensation to the flat buyer
at Rs. 107.60 per sq metres in case of non-delivery of
possession of the residential units in time. Further, alluding to
a revocation deed dated 04.02.2015 entered into by CHB and
the Developer after the arbitral award, learned Counsel argued
that all third party liabilities have now been taken over by the
Developer and can thus not be affixed on CHB. As far as the
liability to return the principal amount is concerned, it was
submitted that 30% of the principal sum has already been paid
by CHB as per Clause 9(d) of the Tripartite Agreement.
However, as regards the interest rate payable on the same, it
8
was contended that the National Commission erred in
enhancing the rate from 9% p.a. to 10% p.a. without giving any
reasons for the same.
6. Per contra, learned Senior Counsel for Respondent No. 1
emphasized that the finding of the arbitrator that both the
Developer and CHB are guilty of breach, and are therefore
liable to make refund of price, interest, or compensation in the
ratio of 70:30, should be given utmost importance. This is
because the order of the National Commission dated
05.03.2013 passed in a similar matter, made the direction as to
the payment of compensation under Clause 9(c) subject to the
outcome of the arbitration proceedings. Similarly, the interim
order of this Court dated 21.04.2015 affirms the findings in the
arbitration award as to the interpretation of Clause 9(c) of the
Tripartite Agreement. Thus, it was argued that in all these
orders, the inter se apportionment of liability has been
relegated in terms of the arbitration award, and therefore, the
ratio of 70:30 stipulated therein should be given effect. Further,
learned Senior Counsel argued that Clause 9(c) was not made
applicable to the instant case, as this clause deals with
compensation payable upon non-performance of obligations,
9
which is different from the nature of compensation awarded in
the impugned order.
7. In addition to this, learned Senior Counsel representing the
Complainant (Respondent No. 2) argued that the amount
awarded to the Complainant vide the impugned order is only in
the nature of a general, lump sum amount and is not the
compensation contemplated under Clause 9(c) of the Tripartite
Agreement. In any case, he submitted that an inter se dispute
between CHB and the Developer as to the apportionment of
liability should not come in the way of the Complainant’s right
to receive compensation.
8. Upon perusing the record and hearing the arguments
advanced by the parties, two issues arise for our consideration
in this appeal:
(a) whether the National Commission was right in
directing the payment of amount towards mental
harassment and litigation costs in the ratio of 70:30, or
whether such amount falls within the purview of
compensation under Clause 9(c) of the Tripartite
Agreement so as to be paid solely by the Developer.
10
(b) whether the interest rate awarded on the principal
sum was rightly increased from 9% p.a. to 10% p.a.
9. As regards the first issue, it would be useful to refer to the
relevant portions of the Tripartite Agreement executed
between the Complainant, CHB, and the Developer on
23.04.2008:
“9. (a) Construction of the residential units is likely to be completed within a period of thirty six (36 months) of the signing of the Development Agreement on 06.10.2006 between the Developer and CHB and/or as may be extended terms of the Development Agreement shall be subject to force majeure and circumstances beyond the control of the developer, and any restrain restrictions from any Courts/Authorities. The delay in grant of development clearances beyond 12 months of the signing of the Development Agreement shall not be counted towards the said portion of 36 months. …(c) In case possession of the built up area is not offered to the buyer within a period of 36 months or extended period as stipulated in sub-clause (a) above, the buyer shall be entitled to receive from the developer compensation @ Rs.107.60 per Sq. Mtrs. (Rs. 10/- per Sq. Ft.) of the super area of the unit per month and to no other compensation of any kind. In case the buyer fails to clear his account and take possession of the unit within 30 days of offer, the buyer shall be liable to pay to the developer holding charges @ Rs. 107.60 per Sq Mtrs. (Rs. 10/- per Sq. Ft.) of the super area of the unit per month in addition to the liability to pay interest to the sellers and other consequences of default in payment.
11
(d) If as a result of any Rules or directions of the Government or if any competent authority delays, withholds, denies the grant of necessary approvals for the Project, or if due to any force majeure conditions, the developer is unable to deliver the unit to the buyer, the developer and CHB shall be liable to refund to the buyer the amounts received from the buyer with interest at the SBI term deposit rate as applicable on the date of refund.”
From the above, it is evident that the Developer and CHB
agreed to complete the construction of the residential units
within a period of 36 months from the date of signing of the
Development Agreement on 06.10.2006. In the event that such
construction was not done, Clause 9(c) would come into
operation and the Developer would become liable to
compensate the buyer at Rs. 107.60 per sq metre of the super
area of the unit, per month.
10. A close reading of Clause 9(c) of the Tripartite Agreement
indicates two salient features– first, the liability to pay
compensation under this Clause can only be affixed on the
Developer if it fails to fulfill the condition under Clause 9(a) and
perform its obligations under the Development Agreement, i.e.
if it does not hand over the possession of the flat to the buyer
within a period of 36 months from the date of signing of the
Development Agreement. The second feature of Clause 9(c) is
12
that it envisages a fixed compensation of Rs. 107.60 per sq
metre per month to be paid to the flat buyer.
10.1 When the facts of the instant case are examined in light
of these observations, it becomes clear that Clause 9(c) is not
attracted in the present case at all. First, there has been no
fulfilment of the condition under Clause 9(a) for Clause 9(c) to
come into operation. This is because the Developer never even
began construction at the project site due to the dispute with
CHB about the encumbrances on the allotted land. Thus, the
question of finishing such construction within the period
mentioned under Clause 9(a) does not even arise.
Consequently, Clause 9(c), which is concerned with the non-
fulfilment of this obligation, is also not attracted. It is notable
that the arbitrator has also arrived at a finding to this effect in
his award dated 09.01.2015 as follows:
“296. Consequently, if any amount is payable on account of refund of price, interest, or compensation (if and when finally determined), respondent is liable to bear and pay 30% thereof, the balance of 70% being payable by the claimant (PDL). Article 14.2.5 no doubt makes the developer solely and exclusively responsible to residential unit buyers, but that is only in regard to non-performance of its obligations. The said provision does not make claimant responsible for the breaches committed by the respondent, nor absolve the respondent from liability for the
13
consequences of its defaults/breaches, which contributed to the non-performance of the obligations by the developer towards the residential unit buyers.”
(emphasis supplied)
Thus, given that the breach of the Development
Agreement is attributable to both, CHB and the Developer, the
failure to hand over possession of the flat to the buyer cannot
be said to be on account of the non-performance of the
obligation of the Developer alone. Consequently, Clause 9(c) is
not applicable to the present case. This reading of Clause 9(c)
has also been affirmed by this Court in its order dated
21.04.2015, and for the reasons mentioned supra, we do not
deem it fit to interfere with the same.
10.2 Secondly, we find that the amount awarded by the
National Commission in the impugned order, i.e. Rs. 1 lakh
each towards mental harassment and litigation costs, cannot
be read as compensation contemplated under Clause 9(c) of
the Tripartite Agreement. Evidently, the litigation costs cannot
be construed as compensation. Even with respect to the award
of Rs. 1 lakh for mental harassment, we find that such amount
is in the nature of a general, lump sum compensation, which
falls short of qualifying as compensation under Clause 9(c). This
14
is especially because there is no mention of the stipulated fixed
rate of Rs.107.60 per sq metre of the super area of the unit, per
month in the impugned order. Thus, the liability of paying a
total of Rs. 2 lakhs under those heads cannot be foisted on the
Developer alone in terms of Clause 9(c).
10.3 Hence, the contention of the learned Counsel for the
Appellant that the impugned order is liable to be set aside on
the ground that the amount towards mental harassment and
litigation costs is in the nature of compensation that is solely
payable by the Developer in terms of Clause 9(c) of the
Tripartite Agreement, cannot be accepted.
11. We also find that the Appellant’s reliance on the
revocation deed dated 04.02.2015 is misplaced, as para 4 of
this deed clearly states that “the parties have accepted the
award” and chosen to act in accordance with the same. Thus, it
cannot be argued that this revocation deed displaces the
arbitration award dated 09.01.2015 and the direction therein
for the Developer and CHB to pay compensation (if and when
determined) in the ratio of 70:30. In any case, this revocation
deed may, at best, arguably settle the rights and obligations or
disputes between the parties in respect of the Development
15
Agreement dated 06.10.2006. In our considered opinion, such
settlement of rights and obligations cannot be extended in a
manner that enables the Developer and CHB to wriggle out of
their liability under the Tripartite Agreement with the
Complainant. Thus, we find that the revocation deed dated
04.02.2015 cannot be invoked by the Appellant to escape its
liability flowing from the Tripartite Agreement and the
arbitration award dated 09.01.2015.
12. We also note that the finding in the arbitration award
dated 09.01.2015 as to the apportionment of liability between
the Developer and CHB to pay the principal sum and general
compensation, must be given effect. To this extent, we find
merit in the argument raised by the learned Senior Counsel for
Respondent No. 1 that the prior National Commission order
dated 05.03.2013 and the subsequent order of this Court dated
21.04.2015 both relegate the inter se apportionment of liability
between the Developer and CHB to the arbitration award. Thus,
the split of 70:30 under the arbitration award must be given
effect, having attained finality.
13. In any case, we find that such division is well-founded as
the sale proceeds from the flat buyers were apportioned in the
16
same ratio of 70:30 between the Developer and CHB. This is
supported by the Escrow Agreement dated 01.06.2007
executed by CHB and the Developer in pursuance of the
Development Agreement dated 06.10.2006. Clause 4(b) of this
Escrow Agreement provides that 30% of the sale proceeds in
respect of the residential units would first be transferred to
CHB, and the remaining amount shall then be transferred to the
Developer. In view of this, we find that the amount directed to
be paid by the National Commission in the impugned order
must be paid by the Developer and CHB in the ratio of 70:30.
14. With respect to the second issue concerning the
enhancement of interest rate, Clause 9(d) of the Tripartite
Agreement is relevant. As mentioned supra, this Clause
requires the Developer and CHB to refund the amounts
received from the buyer with interest if the Developer is unable
to deliver the unit to the buyer due to non-approvals from the
competent authorities. Here, under Clause 9(d), the parties are
liable to refund the principal sum in the ratio of 70:30 as they
had received the sale proceeds in the same ratio. It has been
brought to our notice that CHB has already paid 30% of the
principal sum at 9% interest p.a. in accordance with the
17
directions of the National Commission in order dated
05.03.2013 passed in a similar matter. Notably, the interest
rate was revised to 10% p.a. in the impugned order and has
been challenged by the Appellant. We do not find any reason to
interfere with the same, as the increase was made by the
National Commission in exercise of its discretionary power. It is
possible that the National Commission chose to enhance the
interest rate in view of the fact that it had already imposed
lesser compensation than the significantly higher compensation
stipulated under Clause 9(c). Thus, the contention of the
Appellant on this front is liable to be dismissed.
15. In view of the foregoing observations, we find that the
National Commission was right in directing the Developer and
CHB to pay the principal sum of Rs. 1,03,31,250/- at 10% p.a. to
the Complainant herein. Further, it is found that the direction to
pay Rs. 2 lakhs in toto towards mental harassment and
litigation costs in the ratio of 70:30 between the Developer and
CHB, is also correct.
Accordingly, the instant appeal deserves to be dismissed.
We note that the Appellant herein (CHB) has already paid its
share of the principal sum along with interest at 9% p.a.
18
Further, in pursuance of the order of this Court dated
04.12.2019, the Developer has also deposited the amount
awarded by the National Commission with interest at 10% p.a..
In view of our findings, we now direct CHB to pay the remaining
amount, i.e. 30% of the total Rs. 2 lakhs awarded by the
National Commission to the Complainant towards mental
harassment and litigation charges, as well as an additional
interest of 1% p.a. on its share of the principal sum. This
amount shall be paid within a period of eight weeks from the
date of this order. The instant appeal stands dismissed
accordingly.
…..…………................................J. (MOHAN M. SHANTANAGOUDAR)
.……………………………...............J. (R. SUBHASH REDDY)
New Delhi; December 17, 2019