11 May 2011
Supreme Court
Download

APM TERMINALS B.V. Vs UNION OF INDIA

Bench: ALTAMAS KABIR,CYRIAC JOSEPH, , ,
Case number: C.A. No.-004270-004270 / 2011
Diary number: 13534 / 2010
Advocates: ANUPAM LAL DAS Vs AJAY SHARMA


1

REPORTABLE

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO.4270     OF 2011 (Arising out of S.L.P.(C)No.13893 of 2010)

APM TERMINALS B.V. … APPELLANT

Vs.

UNION OF INDIA & ANR.  … RESPONDENTS

WITH T.C.(CIVIL) NOS.36-37 OF 2010

J U D G M E N T

ALTAMAS KABIR, J.

1. Leave granted in SLP(C)No.13893 of 2010, which  

is being heard along with Transferred Case (Civil)

2

Nos.36-37 of 2010.  While the appeal has been filed  

by APM Terminals B.V. against the decision of the  

High  Court,  dismissing  its  writ  petition,  

challenging the decision of the Board of Trustees  

for the Jawaharlal Nehru Port Trust to exclude the  

appellant from participating in the tender process  

for  the  development  of  the  Fourth  Container  

Terminal at the Bombay Port through public-private  

partnership, the transfer petitions have been filed  

by PSA Sical Terminals Ltd. for transfer of Writ  

Petition Nos.19851 and 19384 of 2010 pending before  

the  Madras  High  Court,  to  this  Court.   As  the  

questions involved in the writ petitions pending  

before the Madras High Court were the same as those  

raised in the appeal filed by APM Terminals B.V.,  

we had directed the transfer petitions to be heard  

along with SLP(C)No.13893 of 2010, out of which the  

present appeal arises.   

2

3

2. In the appeal, the appellant has challenged the  

validity and propriety of the decision taken by the  

Board  of  Trustees  of  the  Jawaharlal  Nehru  Port  

Trust, hereinafter referred to as the “JNPT”, to  

exclude  the  appellant  from  participating  in  the  

tender process for the Fourth Container Terminal  

under the JNPT, through public-private partnership,  

and praying for quashing of the said decision with  

leave to the appellant to participate in the tender  

process in accordance with the policy indicated in  

Circular  No.  PD-12013/2/2005-JNPT  dated  26th  

September, 2007, issued by the Union of India.  The  

further prayer of the appellant was to read the  

provisions of the said Circular into the Licence  

Agreement dated 10th August, 2004, executed between  

the  appellant  and  JNPT,  and,  consequently,  to  

release  the  appellant  from  the  restrictions  

contained in Clause 8.31 of the Licence Agreement  

and/or to treat the same as not binding on the  

appellant.  Clause 8.31 of the Licence Agreement  

3

4

which was executed by the Board of Trustees, JNPT,  

in favour of the appellant, provides as follows :

“8.31 The  Licensee  acknowledges  and  agrees that it shall forego the right to  bid  for  either  directly  or  indirectly,  including  being  a  Management  Contractor  through  any  associate  company,  whether  such company is registered in India or any  other country, or any company in which the  Licensee  has  a  shareholding  for  the  Additional  Facilities  or  existing  facilities  during  the  term  of  this  Agreement.  The Licensee also agrees that  in the event of it or its parent company  taking  over/acquiring/amalgamating/merging  with the licensee or the parent company to  whom the Additional Facilities are awarded  it shall be obliged to divest its stake in  one of the two licenses to a third entity  not linked to the Licensee within 6 months  from the date of such change in control  failing which it shall be deemed to be a  Licensee Event of Default.  The Licensee  also agrees that in the event of it or its  parent  company  being  taken  over/acquired/amalgamated/merged  by  another  licensee  operating  container  facilities at JNPT it shall be obliged to  divest the License to a third entity not  linked  to  the  Licensee  within  6  months  from the date of such change in control  failing which it shall be deemed to be a  Licensee Event of Default.  The Licensee  acknowledges, agrees and accepts the above  as  essence  of  this  Agreement  and  the  Licence granted to the Licensee.”  

4

5

3. Before  the  High  Court,  on  behalf  of  the  

appellant Company, it was claimed that on account  

of subsequent resolutions adopted by the Board of  

Trustees of JNPT, which had the effect of altering  

the  policy  with  regard  to  entrustment  of  

operational  facilities  at  the  port  to  provide  

competition  and  to  prevent  monopolies,  the  

provisions  of  Clause  8.31  would  have  to  be  

reconsidered  in  the  light  of  the  changed  

circumstances.  Before proceeding any further it  

will  be  worthwhile  to  briefly  indicate  the  

background in which the present lis has arisen.   

4. The  Jawaharlal  Nehru  Port  Bulk  Terminal  was  

commissioned on 26th May, 1989, and was designed to  

handle goods imported in bulk, such as fertilizers,  

fertilizer raw materials and food grains, with the  

help of mechanized bulk-handling facilities. With  

the passage of time, the Central Government found  

it  difficult  to  maintain  the  Bulk  Terminal  and  

5

6

decided  to  convert  the  Bulk  Terminal  into  a  

Container Terminal and to remodel the same on a  

Build, Operate and Transfer (BOT) Basis on licence  

for a period of 30 years.  Since 1996, it has been  

the  policy  of  the  Central  Government  to  permit  

participation/investment by the private sector in  

utilizing the assets of the Port, construction and  

creation of additional assets, lease of equipment,  

pilotage, cargo handling, etc.  In fact, guidelines  

had been issued from time to time by the Ministry  

of Surface Transport which was to be followed by  

the Major Ports for private sector participation.  

In pursuance of such policy, the Central Government  

introduced  the  process  of  privatization,  subject  

however,  to  the  regulatory  role  of  the  JNPT.  

Within the regulatory frame-work it was made clear  

that  the  Port  authorities  should  ensure  that  

private investment did not result in the creation  

of private monopolies and that private facilities  

were  available  to  all  users  on  equal  and  

6

7

competitive terms.   

5. The appellant is a Company incorporated under  

the laws of the Netherlands.  Together with the  

Container Corporation of India Limited it formed a  

Joint Venture Company under the name and style of  

“Gateway  Terminals  India  Pvt.  Ltd.”  registered  

under  the  Companies  Act,  1956.   The  said  Joint  

Venture  Company,  hereinafter  referred  to  as  the  

“GTI”,  was  the  successful  bidder  in  the  Tender  

floated  by  JNPT  for  development  of  its  existing  

Bulk  Terminal  into  a  Container  Terminal.  

Thereafter, in keeping with the guidelines issued by  

the  Central  Government  in  1996,  which  were  

described as mandatory, the JNPT floated a Tender  

for the development of a new 600 meter Quay Length  

Container Terminal at Navi Mumbai and Nhava Sheva  

International  Container  Terminal,  hereinafter  

referred  to  as  the  “NSICT”,  was  the  successful  

bidder in respect of the said Tender.  The licence  

7

8

granted  to  NSICT  to  operate  the  first  Container  

Terminal at JNPT culminated in a Build, Operate and  

Transfer  Licence  Agreement  dated  3rd July,  1997  

between JNPT and NSICT which was to subsist for a  

period of 30 years from the date of the agreement.  

Clause 2.3 of the said Licence Agreement provides  

as follows :

“The  License  will  not  bar  the  Licensee  from participating in any subsequent bids  invited by the Licensor for operation of  Container Terminal.”   

6. Accordingly,  NSICT  was  given  liberty  to  

participate in any subsequent bid for operation of  

the Container Terminal.

7. In 2002, JNPT floated another Tender for the  

development  of  the  Second  Container  Terminal  at  

JNPT and invited Requests for Qualification (RFQ)  

for the construction thereof.  In order to prevent  

monopoly  and  promote  competition,  the  JNPT  

subsequently incorporated Clause 1.3 in the Tender  

8

9

documents  for  the  development  of  the  Second  

Container Terminal, which reads as follows :

“Clause  1.3  :  The  port  is  desirous  of  entrusting the Project of redevelopment of the  bulk terminal to a container terminal, on BOT  basis,  to  another  licensee  other  than  the  existing Private Terminal Operator (Licensee)  at  JNPT  i.e.  Nhava  Sheva  International  Container  Terminal  (NSICT)  Limited  or  their  associates,  P&O  or  the  associates,  interconnected or sister companies or either of  them.”  

8. The net result was that NSICT was precluded  

from  participating  in  the  Tender  for  the  

development  of  the  Second  Container  Terminal  at  

JNPT, despite the express provisions of Clause 2.3  

of the Licence Agreement.  

 9. The said decision of the JNPT was challenged by  

NSICT and its affiliate, P&O Australia Ports Pvt.  

Ltd., by way of Writ Petition No.3083 of 2002 in  

the Bombay High Court.  During the hearing of the  

said writ petition, the Union of India and JNPT  

took  the  stand  that  the  1996  Policy  and  the  

9

10

guidelines  would  prevail  over  Clause  2.3  of  the  

Licence Agreement between the said Respondents and  

the  NSICT.   Upholding  the  decision  of  the  

Respondents  to  exclude  P&O  Australia  Ports  Pvt.  

Ltd. and NSICT from participating in the bid for  

the development of the Second Container Terminal,  

the Bombay High Court dismissed the writ petition  

by its order dated 28th January, 2003.  The said  

decision of the Bombay High Court was challenged  

before this Court, which declined to interfere with  

the order of the Bombay High Court.  However, the  

Petitioner’s Joint Venture Company, GTI Pvt. Ltd.,  

was  permitted  to  bid  in  the  Tender  for  the  

development  of  the  Second  Container  Terminal  at  

JNPT.  On completion of the bidding process, the  

work  of  development  of  the  Second  Container  

Terminal was awarded to GTI for a term of 30 years  

from the date of the Licence Agreement which also  

contained Clause 8.31, extracted hereinabove.  In  

fact, before the Bombay High Court, JNPT had taken  

10

11

a  stand  that  Clause  8.31  had  been  subsequently  

incorporated in the Licence Agreement in view of  

the guidelines promulgated in 1996, which were then  

in force.

10. In the meanwhile, on or about 26th September,  

2007, a decision was taken by the Union of India to  

alter  the  1996  policy  and  a  Circular  No.PD-

12013/2/2005-JNPT, was issued indicating that the  

JNPT should proceed to invite global competitive  

bidding for an independent “Stand Alone” Container  

Terminal to expand the Container towards North of  

JNPT by 330 meters, which was designated as the  

Third Container Terminal.  It also clarified the  

eligibility of existing private container terminal  

operators  at  JNPT  to  compete  and  bid  for  any  

project.  In the said Circular dated 26th September,  

2007, it was, inter alia, indicated as follows :

“In the instant case while JNPT is in the  process of undertaking the bidding for the  development of the 330 metre extension of  

11

12

container  berth  towards  North  of  NSICT  project as a stand alone project on BOT  basis (330 metre extension project) there  are  two  different  private  BOT  operators  operating container terminals in JN Port.  As a rational and logical consequence of  the  stand  taken  earlier  it  has  been  decided that the successful bidder of the  previous container terminal on BOT basis  (Maersk A/S – CONCOR Consortium)  and/or  their  subsidiaries/allied  organizations  should  be  excluded  from  bidding  for  the  330 metre extension project.  This would  mean  that  for  the  next  BOT  container  terminal  in  JN  Port  in  future,  the  successful  bidder  of  the  330  metre  extension project would be excluded and so  on.

It has also been decided that the above  convention shall be followed in all Ports  in its true spirit with a view to avoid  monopoly and promote competition till such  time  a  formal  Policy  is  finalized  and  notified.”

11. As a result of the above, neither the appellant  

nor  its  affiliates  and/or  subsidiaries/allied  

organizations were permitted to participate in the  

bid  for  the  Stand  Alone  Container  Terminal.  

Thereafter, in the year 2000, the JNPT floated yet  

another  Tender  for  development  of  the  Third  

12

13

Container Terminal at JNPT, inviting Requests for  

Qualification for selection of a developer for the  

development of the said terminal in which it was  

categorically mentioned as follows:

“JNPT  is  desirous  of  entrusting  this  project  to  a  Licensee  other  than  Maersk  A/S-Concor  Consortium  and/or  their  subsidiaries/allied  organizations  including GTIPL.”

12. The explanation given for the insertion of the  

said clause was to implement the Circular dated 26th  

September,  2007.  GTI’s  plea  to  allow  it  to  

participate in the bid was rejected.  The appellant  

was,  therefore,  subsequently  barred  from  

participating  in  the  Tender  process  for  the  

development  of  the  Third  Container  Terminal  at  

JNPT.  NSICT was, however, allowed to participate  

in the said Tender process for the development of  

the Third Container Terminal at the JNPT UN, but  

such Tender has not yet been finalized.

13

14

13. In  the  meantime,  on  2nd March,  2009,  JNPT  

floated Tender No. PD/N-14th CT/C-60/2009 and issued  

a global invitation of a Request for Qualification  

for development of the Fourth Container Terminal at  

JNPT.   The  said  Tender  contained  the  following  

clause.

“The  successful  bidder/consortium  members  and/or their subsidiaries/allied organiza- tions in the project for the development  of  a  Stand  Alone  Container  Handling  Facility with a key length of 330 meters  towards North at JNPT was to be excluded  from  the  bidding  in  respect  of  Fourth  Container  Terminal  either  as  a  single  applicant or as a consortium.”   

14. On a plain understanding of the above mentioned  

clause,  neither  the  appellant  nor  its  associate  

companies/allied organizations and/or consortium of  

GTI was precluded from participating in the said  

Tender for the development of the Fourth Container  

Terminal  and  raising  its  bid  therein.  The  

appellant, thereupon, along with its letter dated  

5th March, 2009, addressed to the JNPT, forwarded a  

14

15

Demand Draft for Rs.10,000/- towards purchase of  

the RFQ document for participation in the bidding  

process  for  the  Fourth  Container  Terminal.   The  

appellant  was  provided  with  a  copy  of  the  RFQ  

documents,  wherein,  in  Clause  2.2.1(e),  it  was  

categorically stipulated as follows :

“2.2.1(e) To avoid private monopoly and to  promote  competition,  the  successful  bidder/consortium  members  and/or  their  subsidiaries/allied  organization  in  th  project  for  the  “Development  of  a  stand  alone contasiner handling facility with a  quay  length  of  330-m  towards  North  at  NJPT” shall be excluded  from the bidding  for  DEVELOPMENT  OF  FOURTH  CONTAINER  TERMINAL either as a single applicant or  as a consortium.  Further, for the next  BOT  container  terminal  in  JN  Port  in  future,  the  successful  bidder/consortium  members  in  the  DEVELOMENT  OF  FOURTH  CONTAINER  TERMINAL  Project  would  be  excluded and so on.”

15. Even at this stage, JNPT did not preclude the  

appellant from participating in the said tender in  

respect of the Fourth Container Terminal at JNPT.  

The  appellant  was,  thereafter,  invited  to  

15

16

participate in the process for grant of licence for  

the  Fourth  Container  Terminal.   However,  to  the  

surprise of the appellant, on 29th June, 2009, the  

appellant  was  informed  that  GTI  and/or  its  

associates/allied  organizations  had  been  

disqualified from bidding for the Fourth Container  

Terminal  in  view  of  Clause  8.31  of  the  Licence  

Agreement.  As indicated hereinbefore, it was after  

such decision that the appellant, who was worried  

about the rights and entitlements arising out of  

the said Circular, filed Writ Petition No.1551 of  

2008  before  the  Bombay  High  Court  on  29th July,  

2009.  The said Writ Petition was listed before the  

Bombay  High  Court  on  25th August,  2009,  which  

dismissed  the  same  on  10th March,  2010,  relying  

solely  on  the  provisions  of  Clause  8.31  of  the  

Licence Agreement, which disqualified the appellant  

from participating in the Tender process relating  

to the Third Container Terminal.     

16

17

16. It is the said order of the High Court which  

has been challenged in this appeal.

17. Appearing for the appellant, Mr. F.S. Nariman,  

Senior Advocate, submitted that JNPT had awarded  

NSICT,  owned  by  P&O  Ports,  the  licence  for  the  

development  of  the  First  Container  Terminal  at  

JNPT.  Pursuant thereto, JNPT had entered into a  

Licence Agreement dated 3rd July, 1997, with NSICT,  

wherein Clause 2.3, which provided that the said  

licence  would  not  bar  the  licensee  from  

participating in any subsequent bids invited by the  

licensor for operation of the container terminal,  

was  incorporated.   Mr.  Nariman  submitted  that  

despite the 1996 Policy, which aimed at preventing  

monopoly  and  promoting  competition,  the  Licence  

Agreement dated 3rd July, 1997, permitted NSICT to  

participate in the subsequent bids invited by the  

JNPT for operation of the Container Terminal.   

17

18

18. Mr. Nariman submitted that on 26th September,  

2007,  the  Union  of  India  issued  Circular  No.  

PD-12013/2/2005-JNPT  to  JNPT  indicating  that  it  

should  invite  global  competitive  bidding  for  an  

independent,  Stand  Alone  Container  Terminal  

involving a 330 meter extension of container berth  

towards  the  North  of  JNPT.  The  said  Circular  

clarified that existing private Container Terminal  

Operators in JNPT would also be entitled to bid for  

any project but the JNPT was required to ensure  

that  private  investment  did  not  result  in  the  

creation  of  private  monopoly  and  that  private  

facilities were available to all users on equal and  

competitive terms. Paragraph 5 of the 2007 Policy  

clearly provided that the successful bidder of the  

previous  Container  Terminal  on  BOT  basis  and/or  

their subsidiaries/allied organizations, should be  

excluded from bidding for the 330 meter extension  

project.  The immediate fall-out of the same would  

mean that for the next BOT Container Terminal in JN  

18

19

Port in future, the successful bidder of the 330  

meter extension project would be excluded and so  

on.  What was also emphatically stated in paragraph  

6  is  that  it  had  also  been  decided  that  the  

aforesaid guideline should be followed in all Ports  

in its true spirit with a view to avoiding monopoly  

and promoting competition, till such time a formal  

policy  was  finalized  and  notified.   The  2007  

Policy, therefore, provided that MAERSK S/T CONCOR  

Consortium  and/or  their  subsidiary/allied  

organizations would be excluded from bidding for  

the  Third  Container  Terminal  and  the  successful  

bidder  of  the  Third  Container  Terminal  would  be  

excluded from bidding for the next project and so  

on.  Hence, a successful bidder would be ineligible  

to bid for the next but one subsequent tender after  

the immediate one awarded to it.  

19. Mr. Nariman submitted that in accordance with  

the guidelines contained in the 2007 Policy, the  

19

20

appellant  was  specifically  barred  from  

participating  in  the  tender  process  for  the  

development  of  the  Third  Container  Terminal  at  

JNPT.  NSICT who was the successful bidder for the  

first container was allowed to participate in the  

tender  process  for  the  development  of  the  Third  

Container Terminal at JNPT, though the said tender  

is yet to be finalised.

20. Certain problems arose when on 2nd March, 2009,  

JNPT floated Tender No. PPD/M-1/4TH CT/C-60/2009 and  

issued  a  global  invitation  for  Request  for  

Qualification  for  development  of  the  Fourth  

Container  Terminal  at  JNPT,  which  contained  a  

clause  to  the  effect  that  the  successful  

bidder/consortium  members  and/or  their  

subsidiaries/allied  organizations  in  the  project  

for  the  development  of  a  “Stand  Alone  Container  

handling facility with a Quay length of 330 meter  

towards North at JNPT should be excluded from the  

20

21

bidding for the development of the Fourth Container  

Terminal  either  as  a  single  applicant  or  as  a  

Consortium.

21. Mr.  Nariman  submitted  that  the  Request  for  

Qualification  excludes  only  the  successful  

bidder for the Third Container Terminal (which  

is  yet  to  be  awarded)  from  bidding  at  the  

tender  for  the  development  of  the  Fourth  

Container Terminal. Consequently, the appellant  

and/or  its  Associate  Company/allied  

organizations and/or consortium of GTI were not  

precluded from participating in the tender for  

the  development  of  the  Fourth  Container  

Terminal having been precluded from bidding for  

the  “Stand  Alone”  Container  Terminal,  in  

accordance with the 2007 Policy.  It was at  

this stage that JNPT wrote to the appellant on  

29th June, 2009, indicating that it has been  

decided not to allow GTI Pvt. Ltd. and/or its  

21

22

associates to participate in the bidding for  

the  Fourth  Container  Terminal.  Mr.  Nariman  

further submitted that inspite of the decision  

in NSICT’s case, wherein the Union of India had  

relied  on  the  1996  Policy,  it  subsequently  

changed its stand on the strength of the 2007  

Policy indicating that having regard to Clause  

8.31 of the Agreement the appellant was barred  

from bidding for the Fourth Container Terminal.  

22. It was submitted that the stand of JNPT was  

clearly  wrong,  arbitrary  and  discriminatory.  

It was further submitted that the apprehension  

of the JNPT in regard to creation of monopoly  

was  erroneous  and  unrealistic  since  monopoly  

means the power to determine one’s own prices.  

In the case of Ports, the prices for various  

Port  Services  are  determined  by  the  Tariff  

Authority  for  the  Major  Ports  (TAMP)  and  

periodically operators are required to submit  

22

23

their proposed prices to TAMP and cannot charge  

more than the TAMP approved prices for any of  

their services.   It was urged that without the  

power to fix one’s own price, the question of  

monopoly did not arise.   

23. Mr.  Nariman  submitted  that  the  problem  has  

arisen on account of the fact that the tender for  

the  Third  Container  Terminal  is  yet  to  be  

finalised, and, in the meantime the tender for the  

Fourth  Container  Terminal  was  floated.  

Consequently, the Fourth tender was treated by the  

concerned  Respondents  to  be  the  tender  for  the  

Third  Container  Terminal  which  meant  that  the  

appellant  Company  stood  disqualified  from  

participating in the said tender also, since under  

the 2007 Policy it could only participate in the  

next  but  one  subsequent  tender  after  the  one  

awarded to it, thereby suffering double prejudice  

on account of no fault on its part.  Mr. Nariman  

23

24

submitted that to debar the appellant Company from  

participating  in  both  the  Third  as  well  as  the  

Fourth Container Terminals was not justified and it  

should  be  allowed  to  participate  in  the  Fourth  

tender in accordance with Clause 2.3 of its Licence  

Agreement.   Furthermore,  if  the  stand  taken  on  

behalf  of  the  Respondent  was  to  be  accepted,  

despite the supersession of the 1996 Policy by the  

2007  Policy,  the  appellant  would  also  be  barred  

from participating in future tenders for 30 years  

by virtue of Clause 8.31 of the Licence Agreement,  

which would only have the effect of reducing the  

extent of competition which is, in fact, the object  

of the 2007 Policy of the Union of India.  

24. Mr. Nariman also contended that Clause 8.31 of  

the  Licence  Agreement  had  been  imposed  upon  the  

appellant based on the principles of public policy  

and keeping in mind the then prevailing Policy of  

the Government of India, i.e., the 1996 Policy and  

24

25

not out of the free will of the parties.  In any  

event, Clause 8.31 of the Licence Agreement would  

have to be read with the 2007 Policy and could not  

be read in isolation.   

25. Mr. Nariman urged that when the tender for the  

Second  Container  Terminal  was  floated  by  the  

Respondent  No.2,  it  relied  heavily  on  the  1996  

Policy to prevent NSICT from bidding at the said  

tender.  When NSICT challenged the said decision by  

filing a writ petition in the Bombay High Court,  

the Respondents successfully urged before the Court  

in  the  said  Writ  Petition  that  the  1996  Policy  

would  prevail  over  Clause  2.3  of  the  NSICT  

contract.  On  the  other  hand,  as  stated  

hereinbefore,  in  Writ  Petition  No.1551  of  2009  

filed  by  the  appellant,  the  Respondents  took  a  

contrary stand by contending that Clause 8.31 of  

the Licence Agreement would prevail over the 2007  

Policy.  

25

26

26. Mr. Nariman lastly contended that by allowing  

the appellant to raise the technical bid and to  

participate  in  the  pre-bid  meeting  for  the  

development of the Fourth Container Terminal, the  

Respondents  had  given  the  appellant  cause  for  

legitimate expectation of being eligible to bid for  

and be awarded the contract.  Mr. Nariman submitted  

that  the  Respondents  had  acted  in  a  manner  

engineered  to  preclude  the  appellant  from  

participating in the tender for the development of  

the Fourth Container Terminal at JNPT.   

27. Appearing  for  the  Petitioner,  PSA  Sical  

Terminals Ltd., in Transferred Case Nos.36-37 of  

2010,  learned  Senior  Counsel,  Ms.  Nalini  

Chidambaram urged that, although, there was a good  

deal  of  similarity  in  the  issues  raised  in  the  

Special Leave Petition filed by APM Terminals B.V.  

and  the  Transferred  Cases  filed  by  PSA  Sical  

Terminals  Ltd.,  the  substantial  question  in  the  

26

27

Transferred cases was whether a contractual right  

could be superseded by a general policy decision  

under Section 111 of the Major Port Trusts Act,  

1963, without any legislation.  In other words, in  

the facts of this case, could the Petitioner with  

whom a Licence Agreement had been signed on 15th  

July, 1998, by the Respondent No.2, Tuticorin Port  

Trust, with the previous sanction of the Central  

Government under Section 42(3) of the Major Port  

Trusts Act, 1963, be prevented from participating  

in  the  tender  for  additional  facilities  in  the  

Tuticorin  Port,  by  virtue  of  a  policy  decision  

taken in the teeth of the provisions of the Licence  

Agreement which vested the Licensee with the right  

to participate in future tenders.   

28. Ms. Chidambaram urged that after the policy of  

liberalization adopted by the Central Government,  

the  Port  Trusts  permitted  private  operators  to  

operate Container Terminals on a Build, Operate and  

27

28

Transfer basis, through a process of tender.  PSA  

Sical  participated  in  the  Tender  invited  by  the  

Tuticorin  Port  Trust  in  1997  for  operating  the  

Seventh  Berth  at  Tuticorin,  which  was  the  First  

Container  Terminal  and  was  granted  licence  to  

operate the said Berth for 30 years. During the  

subsistence  of  the  guidelines  issued  by  the  

Government  of  India  on  28th October,  1996,  the  

Tuticorin  Port  Trust  entered  into  a  Licence  

Agreement with the Petitioner on 15th July, 1998, to  

operate the Seventh berth and specifically granting  

a right to the Petitioner to participate in any  

subsequent  bids  invited  by  the  said  Trust  for  

operation of additional facilities in the same port  

under  Clauses  2.3  and  6.2.3  of  the  Licence  

Agreement.  For the sake of convenience, the said  

two clauses in the Licence Agreement are reproduced  

hereinbelow :

“2.3 License Period

28

29

The Licence Period shall be for the period  of 30 years (including the time taken for  the  erection  of  container  handling  equipments  at  the  Container  Terminal)  commencing  from  the  Date  of  Award  of  License.

The license will not bar the licensee from  participating  in  any  subsequent  bids  invited by the licensor for development,  designing,  engineering,  constructing,  equipping,  maintaining  and  operating  any  berth or related facility at the port”.

“6.2.3

The  Licensor  agrees  that  it  shall  not  commission additional berths for handling  containers  until  the  traffic  potential  does  not  appear  to  exceed  90%  of  the  maximum volume 1, 25,000 TEUs.  Provided  however  that  the  Licensor  shall  always  consider  future  expansions  of  the  container berths to reasonably match the  market demands and allow the Licensee to  participate in its operation without any  discrimination.  This condition shall be  applicable only within the port limits of  the  Licensor  as  notified  under  Indian  Ports Act, 1908 and Major Port Trusts Act,  1963.”  

29. Ms.  Chidambaram  submitted  that  it  would,  

therefore, be evident from the above clauses that  

notwithstanding  the  1996  guidelines,  while  

29

30

executing the Licence Agreement, the Tuticorin Port  

Trust consciously granted the Petitioner a specific  

right to bid in Tenders for future development in  

the same port and did not consider that the same  

would result in the creation of a private monopoly.  

30. It was submitted that at about the same time,  

the issue relating to the disqualification of Nhava  

Sheva  International  Container  Terminal  (NSICT),  

which was operating the Container Terminal at the  

JNPT and its Associate or interconnected or sister  

companies, including P&O Ports, from participating  

in  the  bid  for  the  re-development  of  the  Bulk  

Terminal  into  a  Container  Terminal  at  JNPT  was  

taken  up  for  consideration  by  the  Bombay  High  

Court.   In the said matter, the JNPT took the  

stand that since P&O Ports was controlling 48% of  

the Container traffic in India and was operating  

the  existing  private  Container  Terminals  at  

Jawaharlal Nehru Port Trust and Chennai, a policy  

30

31

decision had been taken by the Port Trusts of the  

JNPT to debar an existing operator from bidding for  

the  next  Container  Terminal  with  the  object  of  

avoiding concentration of control in one party and  

to  increase  competition  and  efficiency  in  the  

public interest.  The said proposal was forwarded  

to the Central Government which approved the same  

vide its letter dated 11th November, 2002.  

31. Ms. Chidambaram submitted that since P&O Ports  

and  its  associates  were  controlling  48%  of  the  

Container business in India, the Bombay High Court  

upheld the policy of the Central Government aimed  

at  preventing  monopolisation  of  the  container  

business  in  India  by  a  private  party.    Ms.  

Chidambaram submitted that the appeal filed by P&O  

Ports before this Court was also dismissed, with  

this Court upholding the comprehensive guidelines  

that  were  issued  by  the  Government  of  India,  

Ministry of Surface Transport on 26th October, 1996.  

31

32

Ms. Chidambaram, however, urged that the P&O Ports’  

case was decided on facts which were specific to  

P&O Ports and could not, therefore, be treated as a  

precedent for the Petitioner’s case.  However, the  

question  as  to  whether  a  policy  decision  could  

supersede the contractual right was not considered  

by the Bombay High Court or by this Court.  

32. Ms.  Chidambaram  submitted  that  on  31st May,  

2005, the Tuticorin Port Trust invited Tenders for  

development of Berth No.8 into a Container Terminal  

and permitted the Petitioner to participate in the  

tender  process.  The  tender  process  remained  

incomplete for over four years and in 2007 a draft  

policy  was  formulated  to  promote  inter  port  and  

intra port competition in which it was stipulated  

as follows :-

“Wherever the second terminal is to be set  up  at  the  same  major  port,  or  first  terminal in an adjacent major port e.g. JN  Port and Mumbai, Chennai and Ennore Ports,  the  existing  terminal  operator  would  be  

32

33

excluded to ensure competition.  If there  are a minimum of two private operators in  any  major  port,  no  restriction  would  be  placed  on  the  existing  operators  to  bid  for  the  subsequent  terminal,  subject  to  the  condition  that  a  single  private  operator  will  not  be  allowed  to  operate  more than two terminals at the same Major  Port including terminals at adjacent major  port.”

33. Further to the aforesaid approved policy, the  

Government  of  India  wrote  to  the  Tuticorin  Port  

Trust  that  it  had  been  decided  to  debar  the  

existing operator, the Petitioner herein, who was  

operating  the  first  Private  Terminal,  from  the  

bidding process for the second Container Terminal  

at Tuticorin Port in line with the aforesaid policy  

decision.  The  Petitioner  was,  therefore,  denied  

permission from further participation in the tender  

for  the  8th Berth  on  account  of  the  aforesaid  

policy, notwithstanding the specific provision in  

the Licence Agreement permitting the Petitioner to  

participate in subsequent Tenders.   

33

34

34. The  Petitioner  challenged  the  aforesaid  

decision denying permission to the Petitioner from  

participating in the bid for the 8th Berth in Writ  

Petition No.9746 of 2009.  The learned Single Judge  

dismissed the Writ Petition relying on the decision  

in the P&O Ports case.  In the Writ Appeal No.996  

of  2009  filed  by  the  Petitioner  against  the  

decision of the learned Single Judge of the Madras  

High Court, it was submitted on behalf of the Union  

of India that the need for having a second Private  

Container Terminal had been reassessed and that it  

had been decided to scrap the project at the RFP  

stage itself.  The Petitioner’s writ appeal was,  

therefore, dismissed as infructuous.  

35. Subsequently, the Union of India issued a new  

policy  guideline  under  Section  111  of  the  Major  

Port  Trusts  Act,  1963,  on  2nd August,  2010,  and  

immediately  thereafter  on  4th August,  2010,  the  

Tuticorin Port Trust floated re-tender for the 8th  

34

35

Berth  and  restrained  the  Petitioner  from  

participating  therein  in  keeping  with  the  new  

policy guidelines.  Ms. Chidambaram submitted that  

the  2010  Policy  provided  that  if  there  was  one  

private Container/Berth Operator in a Port for a  

specific cargo, the Operator of that Berth or his  

Associates would not be allowed to bid for the next  

Terminal/Berth for handling the same cargo in the  

same  Port.   Ms.  Chidambaram  submitted  that  the  

Petitioner was informed of the said decision of the  

Tuticorin  Port  Trust  by  its  letter  dated  21st  

August, 2010.

36. Aggrieved by the aforesaid decision to debar  

the Petitioner from participating in the bidding  

process for the 8th Berth/Container Terminal, the  

Petitioner filed Writ Petition Nos.19384 of 2010  

and 19851 of 2010, inter alia, for a direction upon  

the  Respondents  to  permit  the  Petitioner  to  

participate in the bid process for the development  

35

36

of the 8th Berth at Tuticorin Port as a Container  

Terminal  and  for  a  further  direction  upon  the  

authorities of the Tuticorin Port Trust to provide  

the  Request  for  Qualification  documents  and  to  

quash the decision not to provide the same.   

37. In the background of the aforesaid facts, Ms.  

Chidambaram  contended  that  a  right  given  to  a  

contractor could be nullified only by a legislation  

specifically  indicating  that  the  agreement  stood  

nullified  and  not  by  a  general  policy  decision.  

Ms.  Chidambaram  submitted  that  while  the  1996  

Policy categorically indicated that the Port should  

ensure that private investment did not result in  

the creation of private monopolies, in the Licence  

Agreement with the petitioner Clauses 2.3 and 6.2.3  

were  included  giving  the  Petitioner  a  right  to  

participate  in  the  bid  for  additional  Container  

Terminals in the same Port.  

36

37

38. Ms. Chidambaram submitted that a draft Policy  

was  prepared  by  the  Central  Government  on  10th  

February,  2005,  to  promote  inter  port  and  intra  

port  competition,  but  the  said  Policy  was  never  

notified and remained a draft.  However, based on  

the draft Policy, the Tuticorin Port Trust invited  

tenders  for  the  8th Berth/Container  Terminal  at  

Tuticorin and allowed the Petitioner to participate  

in the tender process for about 3 years until it  

suddenly took a unilateral decision to debar the  

Petitioner from the bidding process on the strength  

of  a  communication  received  from  the  Deputy  

Secretary,  Ministry  of  Shipping,  dated  22nd May,  

2009.  Ms. Chidambaram submitted that in between  

the aforesaid decision by which the Petitioner was  

debarred from participating in the bidding for the  

8th Berth/Container Terminal at Tuticorin, the Vizag  

Port on 5th June, 2008, took a decision to shortlist  

the existing BOT Operators while recording that the  

same should not be taken as a precedent.  

37

38

39. Ms.  Chidambaram  submitted  that  it  was  

unreasonable  on  the  part  of  the  Respondents  to  

debar the Petitioner from participating in the 8th  

Berth/Container  Terminal  without  formalising  a  

formal  policy  with  regard  to  the  intention  of  

promoting competition and avoiding monopoly.  It  

was also urged that P&O Ports, which had earlier  

been debarred from participating in the bidding for  

the  Second  Container  Terminal  at  the  JNPT,  was  

allowed to participate in the bid for the Third  

Container Terminal, although the P&O Ports and its  

Associates were controlling 48% of the Container  

Terminal business in India and by allowing it to  

participate  in  the  Third  Tender,  the  Central  

Government was, in fact, going back on its desire  

to eliminate monopoly by private Operators within  

the Indian Ports.

40. Ms. Chidambaram urged that it would be apparent  

from the changing policies adopted by the Central  

38

39

Government that they were made to suit a particular  

situation and possibly a particular tenderer. It  

was submitted that even though the First Respondent  

was entitled to change its policies from time to  

time, such changes had to be informed by reason,  

which  was  absent  in  the  instant  case.   Ms.  

Chidambaram  added  that  the  decision  in  the  P&O  

Ports’ case could not be taken to be a precedent as  

far as the Petitioner, PSA Sical Terminals Ltd.,  

was concerned, since P&O Ports was not a party to  

the Licence Agreement at JNP and had no contractual  

right  to  bid  for  the  Second  Container  Terminal  

there.  Although, NSICT had such a right in view of  

Clause  2.3  of  its  Licence  Agreement  to  bid  for  

Container  Terminal  No.7,  it  did  not  assert  its  

right and the same was not also considered in the  

judgment delivered by the High Court.   

41. In support of her submissions, Ms. Chidambaram  

first referred to the decision of this Court in  

39

40

Delhi  Cloth  &  General  Mills  Ltd. Vs.  Rajasthan  

State Electricity Board [(1986) 2 SCC 431], wherein  

the  High  Court  had  quashed  the  decision  of  the  

Rajasthan  Electricity  Board  to  charge  uniform  

tariff  despite  the  prevailing  concessional  rates  

granted  to  a  consumer  under  an  agreement,  upon  

holding  that  only  a  legislative  amendment  could  

override  a  contractual  right  by  specifically  

overriding the contractual terms.   Ms. Chidambaram  

also referred to the decision of this Court in PTC  

India  Ltd. Vs.  Central  Electricity  Regulatory  

Commission [(2010)  4  SCC  603],  wherein,  in  the  

context  of  determination  of  tariff  under  the  

Electricity  Act,  2003,  this  Court  held  that  the  

making of a Regulation under Section 178 of the Act  

became necessary because a Regulation made under  

Section 178 had the effect of interfering with and  

overriding  the  existing  contractual  relationship  

between the regulated entities.   This Court held  

that  a  Regulation  under  Section  178  is  in  the  

40

41

nature of subordinate legislation which could even  

override  the  existing  contracts,  including  Power  

Purchase Agreements, which had to be aligned with a  

Regulation  under  Section  178  and  could  not  have  

been done only on the basis of an order of the  

Central Commission.   

42. Ms.  Chidambaram  reiterated  that  while  the  

Central  Government  was  entitled  to  alter  its  

policies regarding participation of candidates in  

the bid process for the Second Container Terminal  

at the Tuticorin Port, such alteration would have  

to be informed by reason and not on the whims of  

the authorities, which is so apparent in the facts  

of the present case.  Accordingly, in the absence  

of a formal policy regarding the participation of  

candidates  in  the  bid  process  for  the  Second  

Container Terminal of the Tuticorin Port Trust and,  

in particular, the Petitioner, which was covered by  

Clause 2.3 of the Licence Agreement, the Petitioner  

41

42

could not have been barred from participating in  

the tender process for being awarded the contract  

for  the  Second  Container  Terminal  at  Tuticorin  

Port.  Ms. Chidambaram submitted that the decision  

of the Tuticorin Port Trust Authorities to debar  

the  Petitioner  from  participating  in  the  tender  

process  suffered  from  the  view  of  Wadnesbury  

unreasonableness and was liable to be quashed.  

43. The  learned  Solicitor  General,  Mr.  Gopal  

Subramaniam, appearing for the Union of India in  

both the matters, submitted that the case of the  

appellant,  APM  Terminals  B.V.,  and  that  of  the  

Petitioner, PSA Sical Terminals Ltd., stand on a  

similar footing, despite Ms. Chidambaram’s efforts  

to prove otherwise.  The learned Solicitor General  

submitted that the same policy decisions taken by  

the  Central  Government  in  regard  to  private  

participation in the development and operation of  

Container  Terminals  in  the  Major  Indian  Ports  

42

43

governed both the cases, though at different ports.  

The learned Solicitor General submitted that on 26th  

October, 1996, the Union of India issued guidelines  

for all Major Port Trusts regarding private sector  

participation in the major ports.  In the preamble  

of the said guidelines it was indicated that in  

order  to  improve  efficiency,  productivity  and  

quality  of  service,  as  well  as  to  bring  in  

competitiveness  in  port  service,  it  had  been  

decided to throw open the port sector to private  

sector participation.  It was, however, made clear  

in  Clause  4  of  the  policy  statement  that  ports  

would have to ensure that private investment did  

not result in the creation of private monopolies  

and that private facilities were available to all  

users on equal and competitive terms.

44. Pursuant to the said policy decision, the JNPT  

decided to convert the Bulk Terminal which had been  

commissioned  on  26th May,  1989,  and  had  been  

43

44

designed to handle imported fertilizers, fertilizer  

raw materials and food grains through mechanized  

bulk handling facilities, into a Container Terminal  

on  Build,  Operate  and  Transfer  (BOT)  basis  on  

licence for a period of 30 years.  Tenders were  

invited  and,  ultimately,  NSICT  proved  successful  

and was granted such licence by the JNPT for the  

First Container Terminal.  The learned Solicitor  

General submitted that at the said point of time,  

Clause 2.3 was included in the Licence Agreement  

which provided that the Licence Agreement to NSICT  

would  not  prevent  it  from  participating  in  any  

subsequent  bid  invited  by  JNPT  for  operation  of  

Container  Terminals.   However,  in  order  to  give  

effect to its policy decision to prevent private  

monopolisation, the JNPT floated another Tender on  

28th October,  2002,  for  construction  of  a  Second  

Container  Terminal  in  which  Clause  1.3  of  the  

Tender documents provided that JNPT was desirous of  

entrusting the project to another Licensee other  

44

45

than  the  existing  Licensee  at  JNPT  or  its  

associates and interconnected or sister companies.  

The learned Solicitor General submitted that in the  

said process, GTI, a Joint Venture Company of APM  

Terminals and CONCOR proved to be the successful  

bidder.

45. Mr. Subramaniam also indicated that Clause 1.3,  

referred to hereinabove, was challenged by NSICT in  

Writ Petition No.3083 of 2002, before the Bombay  

High Court which dismissed the same and upheld the  

decision to exclude NSICT.  The said decision of  

the  Bombay  High  Court  was  also  upheld  by  this  

Court.   

46. The learned Solicitor General submitted that in  

the  agreement  entered  into  with  GTI  it  was  

specifically  mentioned  in  Clause  8.3  that  the  

Licensee would forego the right to bid for, either  

directly or indirectly, the additional facilities  

or  existing  facilities,  during  the  term  of  the  

45

46

agreement.   It  was  submitted  that  certain  other  

conditions were also stipulated in the said clause  

which  were  aimed  at  preventing  private  

monopolisation of the facilities of the port.

47. The learned Solicitor General submitted that in  

keeping with its aforesaid policy decision, while  

allowing the JNPT to invite Global Tenders for a  

“Stand  Alone”  project,  the  Central  Government  

reminded JNPT of the Government policy formulated  

in October, 1996, to ensure that private investment  

did not create private monopolies.  It was also  

clarified that the policy adopted to exclude the  

existing container operator from the tender for the  

next  container,  would  continue  till  such  time  a  

formal policy was finalised and notified.  It was  

submitted that in the light of such decision, a  

Global invitation was issued by JNPT on 2nd March,  

2009,  for  development  of  the  Fourth  Container  

Terminal at JNPT, and those who had been permitted  

46

47

to participate for the Third Container Berths were  

excluded.  The learned Solicitor General submitted  

that  it  was  only  a  question  of  fortuitous  

circumstances which resulted in the tender for the  

Third  Container  Terminal  remaining  unfinalised.  

Since GTI had been granted licence for the Second  

Container Terminal, it was only in keeping with the  

policy  decision  of  the  Respondents  that  the  

appellant,  APM  Terminals  B.V.,  was  barred  from  

participating in the Tender for the Third Container  

Terminal and was allowed to participate in the bid  

for the Fourth Container Terminal.  If the Tender  

process for the Third Container Terminal had been  

concluded,  the  present  situation  would  not  have  

arisen.  It is only because of the fact that the  

Tender for the Third Container Terminal could not  

be  concluded  that  the  Tender  for  the  Fourth  

Container Terminal was treated to be the Tender for  

the Third Container Terminal and as a result, the  

appellant stood disqualified.   

47

48

48. The  learned  Solicitor  General  submitted  that  

the  Central  Government  was  only  following  its  

decision  to  ensure  healthy  competition  and  to  

prevent the concentration of control of the Major  

Port  Trusts  in  the  hands  of  the  private  sector  

which  could  result  in  unintended  discrimination,  

since  the  private  operators  had  been  given  the  

right to give priority berthing to their own ships  

and other ships could be serviced on a ‘First come  

First served’ basis.   

49. Countering the submissions made by Mr. Nariman  

and  Ms.  Chidambaram  regarding  the  doctrine  of  

legitimate  expectation  and  the  right  of  the  

Government  to  alter  its  policy,  the  learned  

Solicitor General referred to the decision of this  

Court in  Punjab Communications Ltd. Vs.  Union of  

India & Ors. [(1999) 4 SCC 727], wherein, it was  

held  that  a  change  in  policy  could  defeat  a  

substantive legitimate expectation if it could be  

48

49

justified  on  Wednesbury  reasonableness.   The  

learned  Solicitor  General,  therefore,  submitted  

that  the  decision  taken  by  the  Government  to  

prevent private monopoly in the handling of port  

activities was fully justified and could have an  

overriding effect over contractual terms arrived at  

by the Government with a private party.

50. On behalf of the JNPT, it was submitted by Mr.  

Vikas  Singh,  learned  Senior  Advocate,  that  the  

challenge thrown to the order passed by the Bombay  

High  Court,  upholding  the  decision  of  JNPT  to  

exclude  the  appellant  from  participating  in  any  

Tender for development of the port facilities for a  

period of 30 years from the date of signing of the  

agreement, was fully justified.  Mr. Vikas Singh  

submitted  that  in  view  of  Clause  8.3.1  of  the  

Agreement  entered  into  between  JNPT  and  the  

appellant,  it  was  not  open  to  the  appellant  to  

resile from the same.  Furthermore, global tenders  

49

50

had been invited for the construction of the Fourth  

Container facility on 2nd March, 2009 and as per the  

said agreement, the appellant remained ineligible  

to participate in the said Tender also.  Mr. Vikas  

Singh  submitted  that  it  is  no  doubt  true  that  

originally  the  appellant  was  provided  with  RFQ  

documents, but subsequently it was informed that in  

view of Clause 8.3.1 in its Agreement dated 10th  

August, 2004, it was not entitled to participate in  

the  tender  process  for  the  Fourth  Container  

facility.

51. While  adopting  the  submissions  made  by  the  

learned  Solicitor  General,  Mr.  Vikas  Singh  also  

submitted  that  since  the  Tender  for  the  Third  

Container facility had not been proceeded with, the  

Tender for the Fourth Container Terminal would be  

treated to be the Tender for the Third Container  

Terminal  from  which  the  appellant  and  its  

50

51

associates  stood  excluded  on  account  of  the  

existing policy dated 26th September, 2007.   

52. Mr. Vikas Singh submitted that while deciding  

the  Writ  Petition  filed  by  NSICT,  neither  the  

Bombay High Court nor this Court had the benefit of  

the subsequent Constitution Bench decision of this  

Court in PTC India Limited Vs. Central Electricity  

Regulatory Commission [(2010) 4 SCC 603], in which  

this court had held that “regulatory intervention  

into the existing contracts across-the-board could  

have  been  done  only  by  making  Regulations  under  

Section  178  and  not  by  passing  an  Order  under  

Section 79(1)(j) of the 2003 Act”.  Mr. Vikas Singh  

submitted that the appeal filed by APM Terminals  

B.V.  was  without  merit  and  was  liable  to  be  

dismissed.

53. We  have  carefully  considered  the  submissions  

made on behalf of the respective parties and are ad  

idem with the learned Solicitor General that the  

51

52

appeals and the Transferred Cases raise the same  

issue and the only difference between the two is  

that the appellant had not referred to or sought  

the benefit of Clause 2.3 of its agreement, which  

permitted it to participate in future tenders in  

relation to development work within the port area,  

while in the petitioner’s case the same formed the  

main  plank  of  its  claim.   In  substance,  the  

question that we are faced with is whether despite  

the contractual right vested in the appellant as  

well as in the petitioner in the Transferred cases  

to  participate  in  future  tender  processes  for  

developmental work within the port area, such right  

could  be  taken  away  and/or  curtailed  by  a  

unilateral  policy  decision  of  the  Central  

Government.  The further question in the case of  

the appellant is whether having been debarred from  

participating in the bid for the Third Container  

Terminal in JNPT, it could also be excluded from  

the  bidding  process  of  the  Fourth  Container  

52

53

Terminal.   

54. Both  the  Bombay  High  Court  as  well  as  this  

Court have held that in public interest it was open  

to the Government to alter its policies in order to  

subserve  the  common  good  and  that  contractual  

rights would have to give way to the greater public  

interest, which in this case was to prevent the  

creation of private monopolies in the management of  

port facilities in the Major Ports in the country,  

as  this  could  have  far-reaching  and  disastrous  

consequences as far as shipping in such ports was  

concerned.  As already indicated hereinabove, the  

policy  decision  of  26th October,  1996,  made  

provision for privatisation and also gave private  

operators the right to give priority berthing to  

their  own  ships.  The  said  decision  had  the  

potential of substantially disrupting the schedule  

of other ships intending to use the port facilities  

and could discourage foreign ships from coming to  

53

54

Indian Ports and thereby disturb the very pattern  

of the shipping trade in India.

55. While  disposing  of  Writ  Petition  No.8083  of  

2002,  filed  by  P&O  Australia  Ports  Pty.  Limited  

against the Board of Trustees of JNPT, the Division  

Bench  of  the  Bombay  High  Court  examined  the  

question raised herein at length.  It found that  

the appellants were handling container terminals in  

Karachi and Sri Lanka and also at JNP and Chennai,  

thereby  exercising  control  over  48%  of  the  

container traffic in India.  The High Court held  

that the two existing terminals at JNP and Chennai  

are the biggest container terminals in the country  

and  if  the  appellant  and  the  petitioner  in  the  

Transferred Cases were permitted to operate the new  

container terminals also, they would have virtual  

monopoly  of  the  container  traffic  in  the  entire  

country which would not be in the public interest.  

54

55

56.  The High Court also took note of the fact that  

certain shipping agents and their associates had  

expressed  concern  regarding  the  increased  tariff  

charged by the appellant at its container terminals  

at  JNP  and  the  possibility  of  a  monopoly  being  

created by it in the country.  The High Court took  

note of the fact that port authorities all over the  

world had woken up to the possibility of private  

monopolies controlling the use of port facilities  

in such a manner so as to benefit their own ships  

to the detriment of world-wide shipping as a whole.  

The High Court took note of the fact that P&O Ports  

itself had been excluded from bidding for the Third  

Container Terminal in the Port of Melbourne on the  

ground  that  it  would  give  the  said  operator  a  

position of dominance which was to be avoided in  

the  interest  of  the  shipping  industry  at  large.  

Two other examples of Port Klang in Malaysia and  

Bhabange Port in Thailand, were also taken note of  

by  the  Bombay  High  Court  where  different  

55

56

independent  operators  were  appointed  to  promote  

competition.

57. It is precisely for such reason that it had  

become  necessary  for  the  Central  Government  to  

alter  its  policy  decision  regarding  entrusting  

control  of  the  container  terminals  in  the  major  

ports  of  India  in  a  manner  so  as  to  eliminate  

monopolisation and to encourage competition.  The  

decision of the High Court was duly endorsed by  

this  Court  in  SLP(C)No.7488  of  2003  and  it  was  

observed that the High Court had rightly dismissed  

the writ petition.    

58. Insofar as the decision taken by the Central  

Government to alter its policy regarding the grant  

of licence for operating the container terminals in  

the Major Ports in India as against the contractual  

right embodied in the form of Clause 2.3 in the  

agreements  executed  or  entered  into  between  the  

Central  Government  and  the  appellant  and  the  

56

57

petitioner in the Transferred Cases, is concerned,  

the said controversy is no longer valid in regard  

to the appellant, since such point had not been  

taken on its behalf in the writ petition before the  

Bombay  High  Court.   However,  the  same  has  been  

taken  as  a  specific  point  on  behalf  of  the  

petitioner in the Transferred Cases as far as the  

Tenders for the Second Container Terminal at the  

Tuticorin Port are concerned.  The said question  

has to be considered in the light of Article 14 of  

the Constitution and the greater public interest as  

against the contractual right of the individual.

59.  The provisions of Clause 2.3 in the Agreements  

signed  between  the  Tuticorin  Port  Trust  and  PSA  

Sical  cannot  be  read  in  isolation  of  the  other  

provisions  in  the  agreement  which  prevented  the  

Licensee  from  bidding  for  other  work  within  the  

port area during the period of the licence.  In  

fact, in our view, the change in policy to prevent  

57

58

private mobilization has been held to be justified  

by the Bombay High Court as well as this Court.  In  

the absence of any arbitrariness in effecting such  

change in policy and keeping in mind the larger  

public  interest,  we  are  of  the  view,  that  the  

Central Government was within its powers to strike  

a balance  with regard to the control of the port  

facilities so that the same did not come to be  

concentrated in the hands of one private group or  

consortium which would be in a dominant position to  

control not only the rights of tariff, but also the  

entry of ships, not belonging to such group, into  

the Major Ports and thereby give an undue advantage  

to its own ships over other shipping agencies.

60. Normally,  the  Courts  do  not  interfere  with  

policy decisions of the Government unless they are  

arbitrary or offend any of the provisions of the  

Constitution.  In the present cases, the adoption  

of such a course would, in our view, be apposite.

58

59

61. It has been the consistent view of this Court  

that a change in policy by the Government can have  

an overriding effect over private treaties between  

the Government and a  private party, if the same  

was  in  the  general  public  interest  and  provided  

such  change  in  policy  was  guided  by  reason.  

Several decisions have been cited by the parties in  

this regard in the context of preventing private  

manopolisation  of  port  activities  to  an  extent  

where such private player would assume a dominant  

position  which  would  enable  them  to  control  not  

only the berthing of ships but the tariff for use  

of the port facilities.  In both the cases under  

consideration, the same set of entrepreneurs are  

interested in gaining control over the different  

container  terminals  to  the  exclusion  of  other  

players.  The Central Government in its Ministry of  

Shipping and Transport, therefore, took a decision  

not to permit licensees who have been granted a  

licence for running one of the container terminal  

59

60

berths from participating in the bid process for  

the  immediate  next  container  terminal,  with  the  

intention of promoting healthy competition for the  

benefit of the shipping industry and the ports in  

India as well.  The decision to alter its policy is  

based on sound reasoning and the Central Government  

has  taken  such  decision  for  the  benefit  of  the  

consumers as a whole.  The changed policy would  

also have the effect of preventing cartelisation  

and dominant status, which could inevitably affect  

the ultimate pricing of consumer goods within the  

country.   As  was  held  in  Shimnit  Utsch  India  

Private  Ltd. Vs.  West  Bengal  Transport  

Infrastructure Development Corporation Limited and  

Ors. [(2010)  6  SCC  303],  the  Government  was  

entitled  to  change  its  policies  with  changing  

circumstances  and  only  on  grounds  of  change  a  

policy does not stand vitiated.   

60

61

62. It was further held that Government has the  

discretion to adopt a different policy, alter or  

change its policy to make it more effective. The  

only qualifying condition is that such change in  

policy  must  be  free  from  arbitrariness,  

irrationality,  bias  and  malice  and  must  be  in  

conformity  with  the  principle  of  Wednesbury  

reasonableness.  Although, it has been urged by Ms.  

Chidambaram  that  such  change  in  policy  could  be  

effected  only  by  way  of  legislation,  such  a  

submission, if accepted, could stultify the powers  

of  the  Central  Government  to  alter  its  policies  

with changing circumstances for the benefit of the  

public at large.  It is not as if the right of a  

licensee to bid for a further container terminal  

berth has been excluded for the entire period of  

the Licence Agreement but in order to ensure proper  

competition  and  participation  by  all  intending  

tenderers, the said policy has also been altered to  

61

62

enable such licensees to bid for the next but one  

tender as and when invited.

63. However, as far as the appellant is concerned,  

it is because of certain fortuitous circumstances  

that it came to be excluded from the tender process  

for the Fourth Container Terminal.  If the tender  

process for the Third Container Terminal had been  

concluded,  the  various  complications  could  have  

been avoided since under the revised policy, the  

appellant  was  entitled  to  participate  in  the  

alternate bids.  The appellant having been excluded  

from one bid on the basis of an existing policy,  

cannot be debarred from participating in the next  

bid, by taking recourse to a different yardstick.  

Such a course of action would be contrary to public  

policy.  Accordingly, the authorities of the JNPT  

shall  allow  the  appellant  to  continue  to  

participate in the tender process for the Fourth  

Container Terminal and the decision to the contrary  

62

63

conveyed to the appellant on 29th June, 2009, is  

quashed.

64. As  far  as  PSA  Sical  Terminals  Ltd.  is  

concerned, Ms. Chidambaram’s submission as to the  

applicability  of  the  doctrine  of  legitimate  

expectation is at best an expectation if there are  

cogent grounds to deny the same.  The said doctrine  

has  been  explained  by  this  Court  in  Sethi  Auto  

Service  Station Vs.  Delhi  Development  Authority  

[(2009)  1  SCC  180],  and  it  was  held  that  the  

appellant in the said case had certain expectations  

which  were  duly  considered  and  favourable  

recommendations had also been made, but the final  

decision-making  authority  considered  the  matter  

when  the  policy  had  undergone  a  change  and  the  

cases of the appellants therein did not meet the  

new criteria for allotment laid down in the new  

policy.  It was also observed that the concept of  

legitimate expectation has no role to play where  

63

64

State action is based on public policy and in the  

public interest, unless the action taken amounted  

to an abuse of power.

65. As  we  have  indicated  earlier,  the  Central  

Government was within its powers to adopt a policy  

to  prevent  the  port  facilities  from  being  

concentrated in the hands of one private group or  

consortium which could have complete control over  

the  use  of  the  facilities  of  the  ports  to  the  

detriment of the shipping industry as a whole.  The  

decision  taken  by  the  Tuticorin  Port  Trust  

Authorities  to  exclude  PSA  Sical  Terminals  Ltd.  

from bidding for the 8th Berth Container Terminal  

cannot,  therefore,  be  said  to  be  arbitrary  or  

unreasonable  so  as  to  warrant  interference.  In  

fact, the position of PSA Sical Terminals Ltd. is  

no  different  from  that  of  A.P.M.  Terminals  B.V.  

which had been excluded from the bid for the Third  

Container Terminal at JNPT.

64

65

66. In  the  aforesaid  circumstances,  the  appeal  

filed  by  APM  Terminals  BV  is  allowed  and  the  

decision of the Bombay High Court is set aside.  

However, we are also of the view that the decision  

of the Madras High Court does not call for any  

interference and the Transfer Cases filed by PSA  

Sical Terminals Limited are accordingly dismissed,  

but without any order as to costs.

66. All interim orders are vacated.

………………………………………………J. (ALTAMAS KABIR)

                               

………………………………………………J. (CYRIAC JOSEPH)

                              

New Delhi, Dated: 11.05.2011.  

65