AMBALAL SARABHAI ENTERPRISE LIMITED Vs KS INFRASPACE LLP LIMITED
Bench: HON'BLE MR. JUSTICE NAVIN SINHA, HON'BLE MR. JUSTICE KRISHNA MURARI
Judgment by: HON'BLE MR. JUSTICE NAVIN SINHA
Case number: C.A. No.-009346-009346 / 2019
Diary number: 34362 / 2019
Advocates: ANUSHREE PRASHIT KAPADIA Vs
REPORTABLE
IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO(s). 9346 OF 2019 (arising out of SLP (Civil) No(s). 23194 of 2019)
AMBALAL SARABHAI ENTERPRISE LIMITED ...APPELLANT(S)
VERSUS
KS INFRASPACE LLP LIMITED AND ANOTHER ...RESPONDENT(S)
WITH
CIVIL APPEAL NO(s). 9347 OF 2019 (arising out of SLP (Civil) No(s). 23200 of 2019)
HARYANA CONTAINERS LIMITED ...APPELLANT(S)
VERSUS
KS INFRASPACE LLP LIMITED …RESPONDENT(S) CIVIL APPEAL NO(s). 934849 OF 2019
(arising out of SLP (Civil) No(s). 2731127312 of 2019)
NEPTUNE INFRASPACE PRIVATE LIMITED ...APPELLANT(S)
VERSUS
KS INFRASPACE LLP LTD. AND ANOTHER …RESPONDENT(S)
1
JUDGMENT
NAVIN SINHA, J.
The present appeals arise from a common order dated
30.08.2019, passed in three separate miscellaneous appeals filed by
the appellants before the High Court affirming an order of
injunction. K.S. Infraspace LLP Ltd., respondent no.1, filed Special
Civil Suit Nos.322 of 2018 and 323 of 2018 before the Court of
Principal Civil Judge at Vadodara against the appellants in Civil
Appeal No.9346 of 2019 (Ambalal Sarabhai Enterprise) and Civil
Appeal No.9347 of 2019 (Haryana Containers Ltd.) respectively,
which are sister concerns. The appellant in Civil Appeal No.9348 of
2019 (Neptune Infraspace Private Ltd.) was impleaded as defendant
no.2 in the latter suit. The parties shall be referred to by their
respective position in the Civil Suit, for the sake of convenience.
2. The plaintiff filed the two suits for declaration and specific
performance against the defendant sister concerns with regard to a
total area of 19,685 square meters of lands situated in Village
Wadiwadi, Subhanpura, District Vadodara in Gujarat. The plaintiff
contended that there existed a concluded contract with the
2
defendants after negotiations for sale of the suit lands for a total
sum of Rs.31,81,73,076/ and 58,26,86,984/ respectively. The
plaintiff had duly communicated its acceptance of the final draft
memorandum of understanding (MoU) dated 30.03.2018. Only the
formal execution of contract documents remained as a formality. A
sum of Rs.2.16 crores had also been paid as advance. The plaintiff
was ready and willing with the balance amount. Alternately, it was
claimed that there existed a concluded oral contract between the
parties. The Defendants had surreptitiously entered into a
registered agreement for sale with defendant no.2 on 31.03.2018
and thus the suit and prayer for injunction.
3. The Principal Civil Judge by order dated 18.02.2019 held that
by inference the terms and conditions for sale stood finalised by the
email dated 29.03.2018 and 30.03.2018. A token amount of
Rs.2.16 crores had already been paid and the plaintiff was ready
and willing with the balance amount. Creation of third party rights
would lead to further litigation. Thus by an order of temporary
injunction the defendants were restrained from executing any
3
further documents including a sale deed or creating further charge,
interest or deal with the suit lands in any manner.
4. The High Court by its order dated 30.08.2019 affirmed the
order of injunction holding that the communication of acceptance to
the draft MoU sent by email dated 30.03.2018 coupled with the
exchange of WhatsApp correspondences between the parties
amounted to a concluded contract.
5. We have heard learned senior counsel Shri Kapil Sibal, Shri
C.U. Singh and Shri Huzefa Ahmadi, appearing on behalf of
defendant nos. 1 and 2, who are the appellants before us. Shri
Sibal, making the lead arguments on behalf of the defendant sister
concerns submitted that they had decided to sell the lands in view
of financial stringency and their inability to meet financial
commitments interalia leading to attachment of immovable
properties by the Income Tax Department for dues of
Rs.48,74,45,929/ apart from other statutory liabilities, employee
related liabilities and business liabilities. The negotiations with the
plaintiff did not attain finality but remained at the stage of
4
discussions only. The wavering conduct of the plaintiff to meet the
Income Tax liability of the defendants as part of the consideration
amount to facilitate sale by lifting of the attachment, left the
defendants with no other choice but to negotiate afresh with
defendant no.2. The contention that execution of the agreement
remained a formality was disputed. This is evident from the
alternative contention in the suit that there existed an oral contract.
6. The plaintiff’s response of acceptance to the final draft MoU
dated 30.03.2018 was belated. The plaintiff was well aware all along
that the defendants were negotiating with two others also apart from
it. The plaintiff knew before 30.03.2018 that the deal with it was not
coming through and that the defendant was going ahead with
another. The deal with defendant no.2 was finalised by execution of
a registered agreement for sale on 31.03.2018 after defendant no.2
had cleared the Income Tax dues of the sister concerns on
30.03.2018 to the extent of Rs.17.69 crores and Rs.2.20 crores
respectively enabling lifting of the attachment orders for the lands
by the Income Tax department on 26.04.2018 followed by further
payments by defendant no.2 aggregating Rs.45.84 crores till
5
16.01.2019. A sum of Rs. 36.20 crores, from the sale proceeds has
already been utilized by the defendants towards payment of other
statutory liabilities and employee related liabilities etc. It was
therefore a bona fide action. The plaintiff’s email of acceptance of
the draft MoU dated 30.03.2018 as claimed, was not sent by it on
31.03.2018 at 07.43 AM but was received by the defendant on
31.03.2018 at 01.13 PM.
7. Despite the full awareness and knowledge as far back as
30.03.2018 and refund through RTGS of Rs.2.16 crores on
31.03.2018 itself, the plaintiff published a public notice only on
03.04.2018 advising all concerned not to deal with the property
which was duly replied and refuted by another public notice dated
04.04.2018 published by the defendants. The cause of action in the
suit is based on the email dated 30.03.2018 coupled with the public
notice dated 03.04.2018. Acknowledging the refund also on
31.03.2018, it admits the signing of a registered agreement for sale
with defendant no.2 on 31.03.2018 but does not make even a
whisper of a suggestion why the suit was filed more than 7 months
later. In commercial dealings with high stake matters delay is vital.
6
This specific objection on behalf of the defendant taken before the
High Court relying on K.S. Vidyanadam & ors. vs. Vairavan,
1997 (3) SCC 1, has been noticed at paragraph 37 of the judgment
but does not find any consideration.
8. Reliance was also placed on Mandali Ranganna and ors. vs.
T. Ramachandra and ors., 2008 (11) SCC 1 to submit that the
grant of the injunction was contrary to the basic principles
governing injunction more so in a suit for specific performance
relying on Mayawanti vs. Kaushalya Devi, 1990 (3) SCC 1.
9. Shri Huzefa Ahmadi, learned senior counsel appearing on
behalf of defendant no.2, submitted that it was a bona fide
purchaser for value. The plaintiff was well aware of the
simultaneous negotiations with it. The defendant no.2 had made
substantial payments on 30.03.2018 only after obtaining a written
confirmation from the defendant dated 26.03.2018 that it had not
signed any other agreement or received payment from another with
regard to the subject lands. The registered agreement for sale dated
31.03.2018 was followed by delivery of possession much prior to the
institution of the suit. A specific objection with regard to delay was 7
taken in the reply to the injunction application which was not
considered.
10. Dr. A.M. Singhvi, learned senior counsel appearing on behalf of
the plaintiff, submitted that his clients at no stage had declined to
meet the Income Tax liabilities of the defendant sister concerns, as
part of the consideration amount. The negotiations were widespread
over time both by WhatsApp messages and exchange of emails.
These collectively have correctly been interpreted to hold a prima
facie case in favour of the plaintiff. The terms and conditions of
payment, were all finalized which prima facie reflect the existence of
a concluded contract. The fact that the email dated 30.03.2018
referred to the enclosure as a draft MoU cannot be decisive as it has
to be understood on a cumulative assessment of facts. In any
event, the plaintiff had communicated its acceptance without delay
and also protested the refund of the advance of Rs.2.16 crores the
same day followed by a public notice.
11. The hurried manner in which the defendants proceeded to
finalise the deal on 30.03.2018 itself, manifests the desire of the
8
defendants to cause harm to the plaintiff. Defendant no.2 cannot
claim to be a bona fide purchaser as it was all along aware of the
negotiations taking place between the plaintiff and the defendant
sister concerns and that it was at a very advanced stage.
12. Dr. Singhvi framed the question, whether concurrent findings
of the Special Civil Judge and the High Court by two detailed well
considered orders were such as to warrant interference so as to
dissipate the substratum of the suit. In support of his submissions,
Dr. Singhvi relied on Wander Ltd. and another vs. Antox India P.
Ltd., 1990 Suppl. SCC 727, Brij Mohan and others vs. Sugra
Begum and ors., (1990) 4 SCC 147, Motilal Jain vs. Ramdasi
Devi (Smt.) and ors., (2000) 6 SCC 420, Moharwal Khewaji Trust
(Regd.), Faridkot vs. Baldev Dass, (2004) 8 SCC 488, and Aloka
Bose vs. Parmatma Devi and ors., (2009) 2 SCC 582.
13. On the aspect of the delay in institution of the suit, relying on
Mademsetty Satyanarayana vs. G. Yelloji Rao and ors., 1965 (2)
SCR 221, it was submitted that the delay did not induce the
9
defendant to do anything further than that already done earlier, to
their prejudice. In any event the plaintiff is ready and willing to pay
to the defendant no.2 the amount of the Income Tax dues paid by it
and proceed with the contract with the defendant sister concerns.
14. We have been addressed by the counsel for the parties at
length, as also have been taken through the several WhatsApp
messages and emails exchanged. We have also considered the
respective submissions. Litigation at the initial stage of injunction,
where the claims of the parties are still at a nebulous stage, has
stalled the progress of the suit. We are of the considered opinion
that at this stage we ought to refrain from returning findings of facts
or express any opinion on the merits of the suit, except to the extent
necessary for purposes of the present order, so as not to prejudice
either party in the suit.
15. Chapter VII, Section 36 of the Specific Relief Act, 1963
(hereinafter referred to as ‘the Act’) provides for grant of preventive
relief. Section 37 provides that temporary injunction in a suit shall
be regulated by the Code of Civil Procedure. The grant of relief in a
10
suit for specific performance is itself a discretionary remedy. A
plaintiff seeking temporary injunction in a suit for specific
performance will therefore have to establish a strong primafacie
case on basis of undisputed facts. The conduct of the plaintiff will
also be a very relevant consideration for purposes of injunction. The
discretion at this stage has to be exercised judiciously and not
arbitrarily.
16. The cardinal principles for grant of temporary injunction were
considered in Dalpat Kumar vs. Prahlad Singh, (1992) 1 SCC
719, observing as follows :
“5…Satisfaction that there is a prima facie case by itself is not sufficient to grant injunction. The Court further has to satisfy that noninterference by the Court would result in “irreparable injury” to the party seeking relief and that there is no other remedy available to the party except one to grant injunction and he needs protection from the consequences of apprehended injury or dispossession. Irreparable injury, however, does not mean that there must be no physical possibility of repairing the injury, but means only that the injury must be a material one, namely one that cannot be adequately compensated by way of damages. The third condition also is that “the balance of convenience” must be in favour of granting injunction. The Court while granting or refusing to grant injunction should exercise sound judicial discretion to find the amount of substantial
11
mischief or injury which is likely to be caused to the parties, if the injunction is refused and compare it with that which is likely to be caused to the other side if the injunction is granted. If on weighing competing possibilities or probabilities of likelihood of injury and if the Court considers that pending the suit, the subject matter should be maintained in status quo, an injunction would be issued. Thus the Court has to exercise its sound judicial discretion in granting or refusing the relief of ad interim injunction pending the suit.”
17. The negotiations between the plaintiff and the defendant is
reflected in approximately 17 emails exchanged between them
commencing from December 2017 to 31.03.2018. The file size of the
attachment to the mails has varied from 485052485756 KBs
indicating suggestions and corrections from time to time. The
WhatsApp messages which are virtual verbal communications are
matters of evidence with regard to their meaning and its contents to
be proved during trial by evidenceinchief and cross examination.
The emails and WhatsApp messages will have to be read and
understood cumulatively to decipher whether there was a concluded
contract or not. The use of the words ‘final draft’ in the email dated
30.03.2018 cannot be determinative by itself. The email dated
26.02.2018 sent by the defendant at 11:46 AM had also used the
same phraseology. The plaintiff was well aware from the very 12
inception that the defendant was negotiating for sale of the lands
simultaneously with two others. The plaintiff was further aware on
30.03.2018 itself that the deal with it had virtually fallen through as
informed to the escrow agent. The fact that a draft MoU christened
as ‘finalfor discussion’ was sent the same day cannot lead to the
inference in isolation, of a concluded contract. There is no evidence
at this stage that the acceptance was communicated to the
defendant before the latter entered into a deal with defendant no.2
on 30.03.2018 and executed a registered agreement for sale on
31.03.2018. Defendant no.2 paid Rs.17.69 crores and Rs.2.20
crores towards the income tax dues of the defendant the same day,
as part of the consideration amount. It is only thereafter the plaintiff
purports to have communicated its acceptance to the defendant on
31.03.2018 at 01.13 PM. The prolonged negotiations between the
parties reflect that matters were still at the ‘embryo stage’ as
observed in Agriculture Produce Market Committee, Gondal and
ors. vs. Girdharbhai Ramjibhai Chhaniyara and ors., (1997) 5
SCC 468. The plaintiff at this stage has failed to establish that there
was a mutuality between the parties much less that they were ad
idem.
13
18. The pleadings in the suit acknowledge the awareness of the
plaintiff of the ongoing negotiations with defendant no.2. The
advance of Rs.2.16 crores was refunded to the plaintiff in the
evening on 31.03.2018 by RTGS. No effort was made by the plaintiff
to again remit the sum by RTGS immediately or the next day. Only
a public notice was published on 03.04.2018 refuted by the
defendant on 04.03.2018. The suit was then filed seven months
later on 01.10.2018. The explanation that the plaintiff waited
hopefully for a solution outside litigation as a prudent businessman
before finally instituting the suit is too lame an excuse to merit any
consideration.
19. In a matter concerning grant of injunction, apart from the
existence of a prima facie case, balance of convenience, irreparable
injury, the conduct of the party seeking the equitable relief of
injunction is also very essential to be considered as observed in
Motilal Jain (supra) holding as follows :
“6. The first ground which the High Court took note of is the delay in filing the suit. It may be apt to bear in mind the following aspects of delay which
14
are relevant in a case of specific performance of contract for sale of immovable property: (i) delay running beyond the period prescribed under the Limitation Act; (ii) delay in cases where though the suit is within the period of limitation, yet: (a) due to delay the third parties have acquired rights in the subjectmatter of the suit; (b) in the facts and circumstances of the case, delay may give rise to plea of waiver or otherwise it will be inequitable to grant a discretionary relief.”
20. The defendant no.2, in addition to the dues of the Income Tax
department as aforesaid, made further payments to the defendant of
Rs.25,44,57,769/ by 16.01.2019 aggregating to a total payment of
Rs.45,84,71,869/. The defendants had also proceeded to utilize a
sum of Rs.36.20 crores also and had therefore materially altered
their position evidently by the inaction of the plaintiff to institute
the suit in time and having allowed third party rights to accrue by
making substantial investments. In Madamsetty (supra) it was
observed :
“12…..It is not possible or desirable to lay down the circumstances under which a court can exercise its discretion against the plaintiff. But they must be such that the representation by conduct or neglect of the plaintiff is directly responsible in inducing the defendant to change his position to his prejudice or such as to bring about a situation
15
when it would be inequitable to give him such a relief.”
Similar view has been expressed in Mandali Ranganna (supra).
21. We are therefore of the considered opinion that in the facts and
circumstances of the present case, and the nature of the materials
placed before us at this stage, whether there existed a concluded
contract between the parties or not, is itself a matter for trial to be
decided on basis of the evidence that may be led. If the plaintiff
contended a concluded contract and/or an oral contract by
inference, leaving an executed document as a mere formality, the
onus lay on the plaintiff to demonstrate that the parties were ad
idem having discharged their obligations as observed in Brij Mohan
(supra). The plaintiff failed to do show the same on admitted facts.
The draft MoU dated 30.03.2018 in Clause C contemplated payment
of the income tax dues of Rs.18.64 crores as part of the
consideration amount only whereafter the agreement was to be
signed relating back to the date 29.03.2008. Had this amount been
already paid or remitted by the plaintiff, entirely different
considerations would have arisen with regard to the requirement for
16
execution of a written agreement remaining a mere formality.
Needless to state the balance of convenience is in favour of the
defendants on account of the intervening developments, without
furthermore, interalia by reason of the plaintiff having waited for
seven months to institute the suit. The question of irreparable
harm to a party complaining of a breach of contract does not arise if
other remedies are available to the party complaining of the breach.
The High Court has itself observed that from the negotiations
between the parties that “some rough weather was being reflected
between the plaintiff and the defendant ……….”. The Special Civil
Judge failed to address the issue of delay. The High Court noticed
the arguments of the defendants with regard to delay in the
institution of the suit but failed to deal with it.
22. In M.P. Mathur vs. DTC, (2006) 13 SCC 706, this Court
observed :
“14. The present suit is based on equity…In the present case, the plaintiffs have sought a remedy which is discretionary. They have instituted the suit under Section 34 of the 1963 Act. The discretion which the court has to exercise is a judicial discretion. That discretion has to be exercised on wellsettled principles. Therefore, the
17
court has to consider—the nature of obligation in respect of which performance is sought, circumstances under which the decision came to be made, the conduct of the parties and the effect of the court granting the decree. In such cases, the court has to look at the contract. The court has to ascertain whether there exists an element of mutuality in the contract. If there is absence of mutuality the court will not exercise discretion in favour of the plaintiffs. Even if, want of mutuality is regarded as discretionary and not as an absolute bar to specific performance, the court has to consider the entire conduct of the parties in relation to the subjectmatter and in case of any disqualifying circumstances the court will not grant the relief prayed for (Snell’s Equity, 31st Edn., p. 366)….”
23. Wander Ltd. (supra) prescribes a rule of prudence only. Much
will depend on the facts of a case. It fell for consideration again in
Gujarat Bottling Co. Ltd. vs. Coca Cola Co., (1995) 5 SCC 545,
observing as follows :
“47….Under Order 39 of the Code of Civil Procedure, jurisdiction of the Court to interfere with an order of interlocutory or temporary injunction is purely equitable and, therefore, the Court, on being approached, will, apart from other considerations, also look to the conduct of the party invoking the jurisdiction of the Court, and may refuse to interfere unless his conduct was free from blame. Since the relief is wholly equitable in nature, the party invoking the jurisdiction of the Court has to show that he himself was not at fault and that he himself was not responsible for
18
bringing about the state of things complained of and that he was not unfair or inequitable in his dealings with the party against whom he was seeking relief. His conduct should be fair and honest….”
24. The aforesaid discussion leaves us satisfied to conclude that in
the facts and circumstances of the present case, the grant of
injunction to the plaintiff is unsustainable. Resultantly the orders of
injunction are set aside. Nothing in the present order shall be
deemed or construed as any expression of opinion or observation by
us at the final hearing of the suit which naturally will have to be
decided on its own merits. The High Court has already given
directions to expedite the hearing of the suit and we reiterate the
same.
25. The appeals are allowed.
.……………………….J. (Ashok Bhushan)
………………………..J. (Navin Sinha)
New Delhi, January 06, 2020
19